Failure Analysis of a Partially Collapsed Building using Analytical Hierarchical Process

  • Technical Article---Peer-Reviewed
  • Published: 27 October 2020
  • Volume 21 , pages 160–171, ( 2021 )

Cite this article

  • George U. Alaneme   ORCID: orcid.org/0000-0003-4863-7628 1 ,
  • Gregory C. Ezeokpube 1 &
  • Elvis M. Mbadike 1  

320 Accesses

11 Citations

Explore all metrics

Building failure usually results in collapse if not discovered and properly addressed. Building collapse/failure most times causes loss of properties and lives. A case study of a partially collapsed one-story building is presented for emphasis with technical assessment of the partial-collapse cause so as to proffer remedy of the structure. This is achieved through detailed engineering analysis of the building’s structural elements and identification of remedial options. Field inspection is carried out through soil excavation to assess the foundation condition, taking soil samples from the collapsed building for laboratory study and nondestructive test. From inspection, it was observed that the building construction was inadequately supervised and as a result was under-reinforced, which led to excessive cracks and deflection. The soil is classified by AASHTO A-2-4: maximum dry density 2.15 mg/m 3 and optimum moisture content 9%. The compressive strength of the structural elements was measured using the rebound hammer, and a mean compressive strength of 13 N/mm 2 was obtained which indicates a low-compressive-strength concrete. Analytical hierarchical process is utilized as the multi-criteria decision-making method to derive the actual partial-collapse cause; from the priority vector 6, 56, 26 and 12% were obtained for soil/foundation, under-reinforcement, low-compressive-strength and overloading alternatives, respectively. The consistency ratio computed was 0.065 which shows the decision maker’s subjective assessment was consistent. The summary of the failure investigation underscored the importance of ensuring proper supervision and quality control for framed-structures construction.

This is a preview of subscription content, log in via an institution to check access.

Access this article

Price includes VAT (Russian Federation)

Instant access to the full article PDF.

Rent this article via DeepDyve

Institutional subscriptions

building failure case study pdf

Similar content being viewed by others

building failure case study pdf

Observed damage and simplified risk assessment of Italian masonry bell towers struck by past seismic events

Francesco Testa, Alberto Barontini, … Paulo B. Lourenço

Tall building foundations: design methods and applications

Harry G. Poulos

building failure case study pdf

The analysis of failure in concrete and reinforced concrete beams with different reinforcement ratio

Marta Słowik

Abbreviations

Pairwise comparison matrix

Analytical hierarchical process

Priority vector

Random Consistency Index

Consistency Index

Consistency ratio

American Association of State Highway and Transportation Officials

M.A. Salau, Design, construction and maintenance measure for preventing the collapse of reinforced concrete structure. J. Niger. Inst. Struct. Eng. I (1), 1–13 (2005)

Google Scholar  

T.U. Onyemachi, Z.A. Uji, Building failures and it’s implication on real estate investment in Nigeria. AARCHES J. 4 (1), 57–63 (2005)

Mansur Hamma-adama, Obinna Iheukwumere, Tahar Kouider, Analysis of causes of building collapse: system thinking approach. Jordan J. Civil Eng. 14 (2), 188–197 (2020)

M.A. Adetunji, O.I. Oyeleye, O.A. Akindele, Assessment of building collapse in Lagos Island. Nigeria. Am. J. Sustain. Cities Soc. 1 (7), 18–28 (2018). https://doi.org/10.26808/rs.aj.i7v1.04

Article   Google Scholar  

W. Ho, X. Xu, K.P. Dey, Multi-criteria decision making approaches for supplier evaluation and selection: a literature review. Eur. J. Oper. Res. 202 , 16–24 (2010)

J.-Y. Do, D.-K. Kim, AHP-based evaluation model for optimal selection process of patching materials for concrete repair: focused on quantitative requirements. Int. J. Concrete Struct. Mater. 6 (2), 87–100 (2012)

Article   CAS   Google Scholar  

I.G. Chendo, N.I. Obi, Building collapse in Nigeria: the causes, effects, consequences and remedies. Int. J. Civil Eng. Construct. Estate Manage. 3 (4), 41–49 (2015)

G.M. Ayininuola, O.O. Olalusi, Assessment of building failures in Nigeria: lagos and Ibadan as case study. Afr. J. Sci. Technol. 5 (1), 73–78 (2004)

R. Olagunju, S. Aremu, J. Ogundele, Incessant collapse of buildings in Nigeria: an architect’s view. Civil Environ. Res. 3 (4), 49–54 (2013)

T.L. Saaty, An exposition of the AHP in reply to the paper “Remarks on the analytic hierarchy process”. Manage. Sci. 36 (3), 259–268 (1990)

T.L. Saaty, L.G. Vargas, Decision making with the analytic network process: economic, political, social and technological applications with benefits, opportunities, costs and risks (Springer, New York, 2006)

T.L. Saaty, L.G. Vargas, Models, methods, concepts and applications of the analytic hierarchy process (Kluwer Academic Publishers, Boston, 2000)

T.L. Saaty, Axiomatic foundation of the analytic hierarchy process. Manage. Sci. 32 (7), 841–855 (1986)

T.L. Saaty, Decision-making with the AHP: why is the principal eigenvector necessary. Eur. J. Oper. Res. 145 (1), 85–91 (2003)

C.O. Olayinka, S.O. Abiodun, O. Ayodeji, J. Opeyemi, O.B. Daniel, Incessant building collapse in Nigeria: a framework for post-development management control. Develop. Country Stud. 7 (3), 114–127 (2017)

S.A. Oke, A.N. Amadi, A.E. Abalaka, R.T. Akerele, Result of subsoil investigation on a collapsed building site in Lagos. Nigerian J. Construct. Technol. Manage. 10 (1&2), 36–45 (2009)

A.F. Bosede, G.M. Sunday, An investigation on the causes of building collapse in Nigeria. J. Environ. Sci. Resour. Manage. 6 (1), 12–22 (2014)

A.M. Olajumoke, L.A. Oke, A.B. Fajobi, M.O. Ogedengbe, Engineering failure analysis of a failed building in Osun State, Nigeria. J. Failed Anal. Prevent. 9 , 8–15 (2009)

K.C. Onyelowe, G. Alaneme, C. Igboayaka, F. Orji, H. Ugwuanyi, D. Van Bui, M. Van Nguyen, Scheffe optimization of swelling California bearing ratio, compressive strength, and durability potentials of quarry dust stabilized soft clay soil. Mater. Sci. Energy Technol. 2 (1), 67–77 (2019). https://doi.org/10.1016/j.mset.2018.10.005

AASHTO (1995a) Determining the Liquid Limit of Soils. AASHTO Designation: T89-94, Standard Specifications for Transportation Materials and Methods of Sampling and Testing, American association of state highway and transportation officials, 17th Edition, Washington, DC

AASHTO (1995b) Determining the Plastic Limit and Plasticity Index of Soils. AASHTO Designation: T90-94, Standard Specifications for Transportation Materials and Methods of Sampling and Testing, American Association of State Highway and Transportation Officials, 17th Edition, Washington, DC

AASHTO (1993) Particle Size Analysis of Soils. AASHTO Designation: T88-93, Standard Specifications for Transportation Materials and Methods of Sampling and Testing, American Association of State Highway and Transportation Officials, 16th Edition, Washington, DC

AASHTO (1995c) The Moisture-Density Relations Using a 4.45-kg (10-lb) Rammer and a 457-mm (18-in.) Drop. AASHTO Designation: T180-93, Standard Specifications for Transportation Materials and Methods of Sampling and Testing, American Association of State Highway and Transportation Officials, 17th Edition, Washington, DC

M. Bernasconi, C. Choirat, R. Seri, Measurement by subjective estimation: testing for separable representations. J. Math. Psych. 52 (3), 184–201 (2008)

Nucera, F. & Pucinotti, R. (2009). Destructive and Non-destructive Testing on Reinforced Concrete Structure: The Case Study of the Museum of Magna Graecia in Reggio, Calabria

BS 8110: Structural use of concrete, Part 3. British Standards Institution, London (1985)

BS 8110: Structural use of concrete, Part 1. British Standards Institution, London (1997)

BS 6399: Loading for buildings, Part 1 (Code of practice for dead and imposed loads). British Standards Institution, London (1996)

W.H. Moseley, J.H. Bungey, Reinforced Concrete Design, ELBS , 3rd edn. (Chapman and Hall, Hong Kong, 1990)

Book   Google Scholar  

F.K. Kong, R.H. Evans, Reinforced and Prestressed Concrete, ELBS , 3rd edn. (Chapman and Hall, Hong Kong, 1990)

Download references

Author information

Authors and affiliations.

Civil Engineering Department, Michael Okpara University of Agriculture, P. M. B. 7267, Umudike, Umuahia, 440109, Abia State, Nigeria

George U. Alaneme, Gregory C. Ezeokpube & Elvis M. Mbadike

You can also search for this author in PubMed   Google Scholar

Corresponding author

Correspondence to George U. Alaneme .

Ethics declarations

Conflict of interest.

In this research study, there are no recorded conflicts of interests. We also affirm that the content of this work is original and has followed the journal template. Compliance with Ethical Standards was strictly observed.

Additional information

Publisher's note.

Springer Nature remains neutral with regard to jurisdictional claims in published maps and institutional affiliations.

Rights and permissions

Reprints and permissions

About this article

Alaneme, G.U., Ezeokpube, G.C. & Mbadike, E.M. Failure Analysis of a Partially Collapsed Building using Analytical Hierarchical Process. J Fail. Anal. and Preven. 21 , 160–171 (2021). https://doi.org/10.1007/s11668-020-01040-3

Download citation

Received : 12 July 2020

Revised : 27 September 2020

Accepted : 01 October 2020

Published : 27 October 2020

Issue Date : February 2021

DOI : https://doi.org/10.1007/s11668-020-01040-3

Share this article

Anyone you share the following link with will be able to read this content:

Sorry, a shareable link is not currently available for this article.

Provided by the Springer Nature SharedIt content-sharing initiative

  • Building collapse/failure
  • Nondestructive test
  • Compressive strength
  • Construction management
  • Find a journal
  • Publish with us
  • Track your research

Failure Case Studies

  • Information for Faculty
  • Bridge Failure Cases
  • Dam Failure Cases
  • Building Failure Cases
  • Other Failure Cases

2000 Commonwealth Avenue, Boston

An investigation into the collapse of a 17-story concrete high-rise under construction at 2000 Commonwealth Avenue disclosed a number of irregularities and deficiencies, including, among others:

  • Lack of proper building permit
  • Insufficient concrete strength
  • Insufficient length of rebars
  • Lack of proper field inspection
  • Various structural design deficiencies
  • Improper formwork
  • Premature removal of formwork
  • Inadequate placement of rebars
  • Lack of construction control (Kaminetzky 1991)

Four workers were killed and twenty injured.  Fortunately, the collapse occurred slowly enough for many of the workers to escape.  The collapse occurred on January 25, and low temperatures had certainly retarded strength gain.  Cores showed concrete compressive strengths as low as 700 psi (Kaminetzky 1991, Feld and Carper 1997).

Complete case study by Suzanne King:

On January 25, 1971, two-thirds of a 16-story apartment building collapsed while under construction at 2000 Commonwealth Avenue, Boston, MA. Four workers died after a failure on the roof instigated a domino-like collapse all the way to the basement, where the men were found. Fortunately, the collapse took a long enough time for most of the workers to run to safety. This paper investigates the numerous causes and lessons learned of this structural failure.

Introduction

Studying structural failure case studies is a way of studying the history of the engineering profession. Typical calculations for design are based on predicting and avoiding failure. The factor of safety is used to avoid failures, but knowledge of past failures will better equip an engineer to steer clear of future failures. It is not only important to know what caused the failure, but also to understand how it occurred and how to avoid the problem in the future.

In the collapse at 2000 Commonwealth Avenue, Boston, Massachusetts on January 25, 1971, punching shear failure is believed to have triggered the collapse of two-thirds of the 16-story concrete building during construction. But an investigation called for by the mayor proved that there were many flaws in the design of the apartment building. It is important to remind engineers of past failures, such as this one so that history does not repeat itself.

Design and Construction

The high-rise apartment building was made of cast-in-place reinforced concrete flat slab construction with a central elevator shaft. This style of construction is popular for multi-story buildings because it requires a minimum slab thickness and reduces the overall height of the building (Feld and Carper 1997). 2000 Commonwealth Ave. was designed to be sixteen stories with a mechanical room above a five-foot crawl space on the roof. The structure also had two levels of underground parking. A swimming pool, ancillary spaces, and one apartment were located on the first floor and one hundred thirty-two apartments were on the second through sixteenth floors. Originally these apartments were to be rented, but the owners later decided to market them as condominiums.

Construction began on the site late in the fall of 1969. Excavation had been partially started a few years earlier. Most of the work was subcontracted to area specialists. Only one representative from the General Contractor was on site during construction. At the time of the collapse, construction was nearing completion. Brickwork was completed up to the sixteenth floor and the building was mostly enclosed from the second to fifteenth floors. Plumbing, heating and ventilating systems were being installed throughout various parts of the building. Work on interior apartment walls had also started on the lower floors. A temporary construction elevator was located at the south edge of the building to aid in transporting equipment to the different floors. It is estimated that one hundred men were working in or around the building at the time of failure (Granger et al. 1971).

After interviewing many eyewitnesses, the mayors investigating commission concluded that the failure took place in three phases. These phases were punching shear failure in the main roof at column E5, a collapse of the roof slab, and, finally, the general collapse.

Phase 1: Punching Shear Failure in the Main Roof at Column E5

At about ten in the morning, concrete was being placed in the mechanical room floor slab, wall, wall beams, and brackets. Placement started at the west edge and proceeded east. Later in the afternoon, at about three o’clock, most of the workers went down to the south side roof for a coffee break. Only two concrete finishers, Mr. Daniel Niro and Mr. Joseph Oliva, remained on the pouring level near line 4-1/2. Shortly after the coffee break, the two men felt a drop in the mechanical room floor of about one inch at first and then another two or three inches a few seconds later. The labor foreman, Mr. Anthony Paolini, was directing the crane carrying the next bucket of concrete. He instructed the operator to “hold the bucket” and went down to the sixteenth floor by way of a ladder in the east stairway. That is when the punching shear was noticed around column E5. The carpenter foreman, Mr. Antonio M. Fantasia, was also in the area and immediately yelled a warning to the men working on the sixteenth floor and roof of a possible roof collapse. The slab had dropped five or six inches around the column and there was a crack in the bottom of the slab extending from column E5 toward column D8. Column E5 is located directly below where the concrete was being placed for the mechanical room floor slab on the east side of the building as shown in the following figure (Granger et al. 1971).

Phase 2: Collapse of the Roof Slab

After hearing Mr. Fantasia’s warning, most of the workers in the area of column E5 managed to run to an east balcony and stay there until after the roof slab collapse. Eyewitness testimony concluded that the collapse happened fairly quickly. The roof slab began to sag in the shape of a belly and reinforcing steel started sticking out from the mechanical room floor slab. Soon everything started to shake and the east half of the roof slab collapsed onto the sixteenth floor. Then it stopped, giving the workers a chance to run down the stairs to the ground. At the time of failure, the Structural Subcontractor was placing reinforcing steel for the stairs on the fourteenth and fifteenth floors on the east side of the building. So when the workers were making their way from the roof and floors above, most of them crossed over to the west side of the building when they reached the fifteenth floor. (Granger et al. 1971)

Phase 3: General Collapse

After the roof collapsed, the roof settled and most of the stranded workers could be rescued using the crane and construction elevator. However, about twenty minutes after the roof failed, the east side of the structure began to collapse. A resident of 1959 Commonwealth Ave. described the collapse as a domino effect (or progressive collapse). The weight of the collapsed roof caused the sixteenth floor to collapse onto the fifteenth floor, which then collapsed on the fourteenth floor, and so on to the ground (Litle 1972). At first, the different floors were distinguishable, but later dust and debris made it difficult to discriminate between the various floors. When the dust finally settled, two-thirds of the building had collapsed. The east side and areas on either side of the elevator shaft were gone. Four workers were killed during the collapse and thirty workers suffered injuries (Granger et al. 1971).

The extent of the collapse is shown in the photographs in APPENDIX B. The first picture is from the February 4, 1971, issue of EngineeringNews-Recordd. This picture shows the floor slabs hanging from individual floors. Only the west side of the building remains standing. The next photograph is a close-up of the collapse. It shows the exposed elevator shaft. The building collapsed around the interior elevator.

Causes of Failure

A week after the collapse, Engineering News Record reported that there were three possible causes of structural failure under investigation: formwork for the penthouse floor slab collapsed onto the roof, a heavy piece of equipment fell from a crane and started the progressive collapse or concrete placed during previous cold days had failed (ENR, February 4, 1971). However, after an extensive investigation, the mayor’s commission concluded that there were many design and construction flaws that attributed to the collapse. The committee determined that punching shear failure at column E5 triggered the initial collapse. This type of failure is caused by unbalanced moments transferred between the column and flat-plate (Megally and Ghali 2000) and was a result of non-conformities to the design documents. The major areas that construction did not follow the design were shoring and concrete strength. Inadequate sharing under the roof slab on the east side of the building made it impossible for the roof to hold the freshly placed concrete for the mechanical room floor slab, construction equipment and two boilers that were stored on that side of the building. Also, the concrete strength of the roof slab was well below three thousand pounds per square inch as specified in the design. However, there were many other factors, design and procedural, that contributed to the collapse (Granger et al. 1971).

Design Concerns

The design concerns that contributed to the collapse include insufficient length and placement of rebar and various structural design deficiencies. All of the reinforcing steel used was designed to be billet steel, however, a large amount of rail steel was found in columns and slabs on the lower floors. The major difference between rail and billet steel (as described in the Commission’s report) is the ultimate elongation. The average ultimate elongation for rail steel used on the project was just over ten and a half inches as opposed to a little over fifteen and a quarter inches for the billet steel. This variance would effect how the floor slabs reacted to tension forces. Also, the steel was delivered by the supplier in bundles with marks on the steel indicating what the steel was intended for. However, some of the marks used were the same as the marks on the design plans, yet meant something different. For example, the supplier gave marks for number four bars at the south edge of the slab which was identical to marks given on the Engineers placing drawings for top slab bars over column E5 (Granger et al. 1971). There were also design errors in the reinforcement. Some of the bars did not extend long enough into the columns as required by code and placement of bars in some of the slabs was not sufficient to meet the American Concrete Institutes (ACI) code at the time. There was also inadequate design around columns. ACI requires that at least twenty-five percent of the negative slab reinforcement in each column strip pass over the column within a distance of “d” on either side of the column face (Granger et al. 1971). This requirement was not fulfilled.

Procedural Concerns

There were many procedural concerns in the construction of 2000 Commonwealth Ave. Nearly every step of construction was flawed (Kaminetzky 1991). Some of the major concerns include lack of proper building permit and field inspection, premature removal of formwork, and lack of construction control.

The investigating committee determined that if the construction had had a proper building permit and followed codes, then the failure could have been avoided. Since there were numerous problems that all aided to the collapse, deciding whom to hold responsible for the collapse became a difficult feat. Ownership changed hands many times and most jobs were subcontracted. Some of the transactions that took place with Bostons Building Department are listed in the table below (Granger et al. 1971). There was confusion surrounding the project from the start.

Construction did not follow the Structural Engineers specifications for shoring or formwork. Before removal of shores and forms, the concrete must first reach seventy percent of its designated twenty-eight-day strength. It was the commission’s opinion that despite seven-day cylinder tests that said otherwise, the average strength of the concrete in the roof slab was only nineteen hundred pounds per square inch after at least forty-seven days, not the required twenty-one hundred pounds per square inch for removal or the specified three thousand pounds per square inch required after twenty-eight days. There was no inspection or cylinder testing done for the east side of the building, so removal of formwork was based on values obtained from the west side of the building. Furthermore, adequate shoring under the roof slab below the freshly place mechanical room floor slab was not used (Granger et al. 1971).

Finally, there was very little construction control on the site. There was no architectural or engineering inspection of the project and the inspection done by the city of Boston was inadequate. The design plans specifically stated that certain aspects of the project needed to be approved by an architect, yet no architect or engineer was consulted. The Affidavit Engineer and Licensed Builder were also nowhere to be found. Instead, construction was based on arrangements made by the subcontractors. As mentioned before, there was only one representative from the General Contractor and this man was not a licensed builder. He did not direct, supervise or inspect any of the work done by the subcontractors (Granger et al. 1971).

Similarities to Other Failures

The progressive collapse of 2000 Commonwealth Ave. was similar to the structural failures of buildings in Bailey’s Crossroads and Harbour Cay . On March 2, 1973, the Skyline Plaza in Baileys Crossroads, Virginia collapsed while under construction. Like 2000 Commonwealth Ave., premature removal of shoring and insufficient concrete strength were the causes of failure (Woodward et al. 1983). The collapse of the flat-plate Harbour Cay condominium building in Cocoa Beach, Florida on March 27, 1981, was caused by punching shear failure triggered a progressive collapse (Lew et al.1983), much like 2000 Commonwealth Ave. Investigations following the three collapses concluded that both design and construction errors contributed to the cause of the collapse. All three failures could have been avoided if better inspections of materials and construction details were conducted.

References:

  • Feld, J., and Carper, K. (1997). Construction Failure. 2 nd Ed., John Wiley & Sons, New York, N. Y
  • Granger, R. O., Peirce, J. W., Protze, H. G., Tobin, J. J., and Lally, F. J. (1997), The Building Collapse at 2000 Commonwealth Avenue, Boston, Massachusetts, on January 25, 1971 , Report of the Mayor’s Investigating Commission, The City of Boston, Massachusetts.
  • Kaminetzky, D. (1991). Design and Construction Failures: Lessons from Forensic Investigations . McGraw-Hill, New York, N. Y.

Illustrations from Chapter 5 of the book Beyond Failure: Forensic Case Studies for Civil Engineers, Delatte, Norbert J., ASCE Press.

  • Search for:
  • Make a Gift
  • Maps / Directions

Facebook

Join TheConstructor to ask questions, answer questions, write articles, and connect with other people. When you join you get additional benefits.

Confirm Password *

First Name *

Last Name *

Country Select a country… Åland Islands Afghanistan Albania Algeria Andorra Angola Anguilla Antarctica Antigua and Barbuda Argentina Armenia Aruba Australia Austria Azerbaijan Bahamas Bahrain Bangladesh Barbados Belarus Belau Belgium Belize Benin Bermuda Bhutan Bolivia Bonaire, Saint Eustatius and Saba Bosnia and Herzegovina Botswana Bouvet Island Brazil British Indian Ocean Territory British Virgin Islands Brunei Bulgaria Burkina Faso Burundi Cambodia Cameroon Canada Cape Verde Cayman Islands Central African Republic Chad Chile China Christmas Island Cocos (Keeling) Islands Colombia Comoros Congo (Brazzaville) Congo (Kinshasa) Cook Islands Costa Rica Croatia Cuba CuraÇao Cyprus Czech Republic Denmark Djibouti Dominica Dominican Republic Ecuador Egypt El Salvador Equatorial Guinea Eritrea Estonia Ethiopia Falkland Islands Faroe Islands Fiji Finland France French Guiana French Polynesia French Southern Territories Gabon Gambia Georgia Germany Ghana Gibraltar Greece Greenland Grenada Guadeloupe Guatemala Guernsey Guinea Guinea-Bissau Guyana Haiti Heard Island and McDonald Islands Honduras Hong Kong Hungary Iceland India Indonesia Iran Iraq Isle of Man Israel Italy Ivory Coast Jamaica Japan Jersey Jordan Kazakhstan Kenya Kiribati Kuwait Kyrgyzstan Laos Latvia Lebanon Lesotho Liberia Libya Liechtenstein Lithuania Luxembourg Macao S.A.R., China Macedonia Madagascar Malawi Malaysia Maldives Mali Malta Marshall Islands Martinique Mauritania Mauritius Mayotte Mexico Micronesia Moldova Monaco Mongolia Montenegro Montserrat Morocco Mozambique Myanmar Namibia Nauru Nepal Netherlands Netherlands Antilles New Caledonia New Zealand Nicaragua Niger Nigeria Niue Norfolk Island North Korea Norway Oman Pakistan Palestinian Territory Panama Papua New Guinea Paraguay Peru Philippines Pitcairn Poland Portugal Qatar Republic of Ireland Reunion Romania Russia Rwanda São Tomé and Príncipe Saint Barthélemy Saint Helena Saint Kitts and Nevis Saint Lucia Saint Martin (Dutch part) Saint Martin (French part) Saint Pierre and Miquelon Saint Vincent and the Grenadines San Marino Saudi Arabia Senegal Serbia Seychelles Sierra Leone Singapore Slovakia Slovenia Solomon Islands Somalia South Africa South Georgia/Sandwich Islands South Korea South Sudan Spain Sri Lanka Sudan Suriname Svalbard and Jan Mayen Swaziland Sweden Switzerland Syria Taiwan Tajikistan Tanzania Thailand Timor-Leste Togo Tokelau Tonga Trinidad and Tobago Tunisia Turkey Turkmenistan Turks and Caicos Islands Tuvalu Uganda Ukraine United Arab Emirates United Kingdom (UK) United States (US) Uruguay Uzbekistan Vanuatu Vatican Venezuela Vietnam Wallis and Futuna Western Sahara Western Samoa Yemen Zambia Zimbabwe

By registering, you agree to the Terms of Service and Privacy Policy . *

Log in to TheConstructor to ask questions, answer people’s questions, write articles & connect with other people. When you join you get additional benefits.

Join for free or log in to continue reading...

Username or email *

Forgot Password

Lost your password? Please enter your email address. You will receive a link and will create a new password via email.

Sorry, you do not have permission to ask a question, You must log in to ask a question. Join now!

The Constructor Logo

The Constructor

3 important cases of building collapse due to poor construction management.

Do you need to remove the ads? Join now!

🕑 Reading time: 1 minute

Construction is perhaps the most critical stage in the life cycle of structures, mainly because of the danger of failure and the high chances of underestimating construction loads.

A report developed by the American Society of Civil Engineers, based on their study of around 600 failed structures, found that around 40% of the structures failed during the construction stage, 36% of the structures failed during the pre-construction stage due to flawed designs, and 24% failed during their operational stage.

The failure of a structure is described as the propagation of local collapse from one segment to another segment, eventually resulting in the failure of an entire building or its lopsided part. It could be a product of natural disasters, for example, seismic tremors, floods, or coincidental acts such as an explosion in the service system or terrorist bombings.

Failure of a building in Bangladesh due to poor-quality concrete

Analyzing the reasons for explicit structural failures and proposing measures to relieve their effects is a successful measure to lessen risks and improve the safety of structures. Therefore, this article discusses the failure of some major structures, their root causes, and the lessons learned. 

1. The Skyline Plaza Apartment Building, Virginia, US

The design plan of the Skyline Plaza complex included six office buildings, eight apartment buildings, shops, and one hotel. The project was a $200 million residential-commercial complex and was situated in Fairfax County, Virginia. During the construction of the skyline plaza complex, one of the apartment buildings under construction collapsed. A total of 15 labors were killed, and 40 were injured.

Design drawings of the collapsed building included the construction of 26 stories, a penthouse, and a four-story storm basement for parking. The building design was of a reinforced concrete flat plate with a 200 mm thick concrete slab. The height between each story was 2.7 m. 

the collapse of the Skyline Plaza Apartment Building was due to poorly managed construction processes

1.1 Investigation Findings 

On 2 nd March 1973, some portion of the apartment building collapsed during construction. The collapse began on the 23 rd floor when the slab of the 24 th floor was being cast. On the 23 rd floor, the slab started showing cracks and the failure of the building occurred vertically along the full height of the building, including the basement levels. Also, the adjacent post-tensioned reinforced concrete car parking structure collapsed. 

Specialists concurred that the concrete had not acquired sufficient strength to carry the construction loads applied during the construction process. Investigators confirmed that the original design plan had no deficiencies. The most probable reason for the collapse of the building was the punching shear failure on the 23 rd floor of the building.  

After the collapse, a team from the Occupational Safety and Health Administration (OSHA) came to the site and started an investigation. Further, a detailed investigation was conducted by the National Bureau of Standards (NBS). 

NBS and OSHA mentioned in their reports that the collapse of the building was directly related to poorly managed construction processes. The court found that the contractor and the site engineer were guilty of negligence as the contractor didn't follow the building code requirement and the site engineer didn't inspect the work properly. 

1.2 Lessons Learned

After the collapse of the Skyline Plaza apartment building, a series of changes were made in the building code related to the progressive collapse failure. Special inspection procedures were added in the inspection section of the building codes. Design criteria were also changed for effective planning to reduce the possibility of failure due to progressive collapse. The following points describe the violations of specified construction requirements and standard practices: 

  • Violation of prerequisites to completely shore the two stories underneath the floor being cast. 
  • Failure to permit legitimate curing time before removing shoring. 
  • Failure to conduct curing test on the concrete specimen in the field. 
  • Use of out-of-plumb shoring. 
  • Improper inspection during casting and formwork removal to check the strength of concrete.  
  • Improper installation of the climbing crane. 

2. Ronan Point Tower, Canning Town ,   London

The need to give substitution lodging to homes destroyed in World War-II encouraged European engineers to develop innovative pre-assembled construction strategies. One such plan included the construction of high-rise buildings using pre-stressed concrete components made in factories.

The structural framework included the construction of load-bearing walls and each floor was directly stacked onto the walls. Grouted bearing surfaces were used to construct the joint between the wall and the floor. This process of construction was termed as system building. A skyscraper at Ronan Point, Canning Town, UK, was built using this system building technique. 

On 16 th May 1968, a blast occurred due to gas leakage in the kitchen of a house on the 18 th floor. Just after the blast, the kitchen walls collapsed, and in-turn, the walls above the 18 th floor caved in. This impacted the floors beneath and obliterated the entire corner of the structure. A total of 14 people were injured and three were killed. 

The progressive collapse of the Ronan Point Tower occurred because there were no alternative load paths when one part of an external wall at one level was failed

2.1 Investigation Findings 

The investigation team revealed that the building collapsed due to the non-availability of an alternative load path when one portion of the external wall collapsed. After the demolition of the building, it was also revealed that the quality of the grouted bearing surface for the joints between floors and the walls was poor.

Because of the unprecedented collapse, the government examined the safety of other buildings constructed using the same concept as the Ronan Point Tower. Many buildings were demolished well ahead of their life span. 

The concept of progressive collapse of structures was not much known to the engineers before the failure of the Ronan Point Tower. In such collapses, a local failure is followed by widespread collapse through a chain reaction. What was irregular on account of the failure of the Ronan Point Tower was that a minor gas blast set off the collapse of a huge portion of a finished structure.

2.2 Lessons Learned

The experience due to the failure of Ronan Point Tower re-emphasized the following points: 

  • Progressive failure can also occur in fully constructed structures.
  • A structure should have redundancies to reduce the possibility of progressive failure. 
  • Quality control should strictly be followed in the construction processes. 

3. 2000 Commonwealth Avenue, Boston, US

On 25 th January 1971, a two-third portion of a 16-story residential building known as 2000-Commonwealth Avenue in Boston collapsed during construction, leading to the death of four workers. The building was under construction for more than six years. The collapse of the building generated approximately 8000 tons of debris. Luckily, the failure of the building was gradual, giving the workers some time to escape from the building site. 

The building was designed as a reinforced concrete structure and flat slabs were used for the roofing system with an elevator shaft provided in the center. This type of structural design is mainly famous for multi-story construction as it reduces the thickness of the slab and overall height between the floors. The thickness of flat slabs was between 160-190 mm for all the building areas except near the elevator core where it was 230 mm thick. The arrangement of the structural component constituted a height of 2.7 m for all the floors.    

The building, situated at 2000 Commonwealth Avenue, was intended to be 16 stories high with a mechanical room of height 1.5 m for the working of the lift at the rooftop. The plan area of the structure was 56 x 21 m 2 . The building additionally had underground parking of two levels. A pool, auxiliary spaces, and one flat were situated on the first floor, and a total of 132 flats were on the second through sixteen floors. At first, these flats were to be leased. However, the proprietors later chose to advertise them as apartment suites. 

At the hour of the collapse of the building, construction work was almost completed. The brickwork was finished up to the sixteenth floor, and the structure was generally encased from the second to the fifteenth floor. Heating, plumbing, and ventilation frameworks were introduced all through different floors of the structure. The interior work had also started on the lower floors. A temporary lift was constructed to help in moving equipment to various floors. It was assessed that 100 individuals were working in or around the structure at the hour of the collapse. 

The collapse of the building occurred in three stages. These stages were, failure due to punching shear in the rooftop at section E5, the failure of the slab, and in the end, the progressive failure of the structure. 

Collapse of the 2000 Commonwealth Avenue occurred due to the development of punching shear mechanism around column.

3.1 Investigation Findings 

The civic chairman of Boston appointed a commission to inquire about the collapse of the building. The commission discovered the following critical observations: 

  • There was no signature of an architect or engineer found on a single drawing of the building. 
  • The design engineer didn't give the computations supporting his structural drawings to the commission. No head or representative of the team of contractors held a building construction license of Boston city. 
  • Ownership of the venture changed a few times, with changes in planners and architects. This scenario added to the general disarray and contributed to the abnormalities referred above. 
  • The general contractual worker just had a solitary representative on location. Most subcontracts were given directly by the owner to the subcontractors and bypassed the general contractor. A total of seven subcontractors were involved in the construction. 
  • The subcontractor, who was assigned to conduct the cold weather protection work on the structural concrete didn't carry out the assigned work. However, the structural engineer had indicated these measures. 
  • There was no proof of any inspection of the work by a specialist despite the fact that the project particulars needed this. 
  • The quality of construction material and quality inspections were poor. 
  • The collapse of the building occurred due to the development of punching shear mechanism around column E5. Punching shear developed the flexural cracks around the roof slab located near the elevator core. Thus, the slab collapsed due to flexural yielding. 
  • The design manual indicated a 28-day strength of 25 MPa. However, at the failure time, 47 days after casting work, the concrete couldn't seem to attain the necessary 28-day strength. 
  • The most critical inadequacies were an absence of shoring under the slab at the roof and the quality of the concrete.

3.2 Lessons Learned

The following key factors describe the collapse of the multi-story building situated at 2000 Commonwealth Avenue: 

  • Authorized design engineers should be chosen for the development of working drawings for construction. 
  • Engineers and architects should be responsible for all the design-related calculations and their design work must be examined by the experts in that field from a government organization. 
  • Ownership of a project should not change multiple times to reduce the confusion between the previous engineer and the newly appointed engineer. 
  • Inspection at the construction site should be conducted regularly by government organizations, especially for cold weather work.  
  • The quality of concrete work should be monitored throughout the project. 
  • The construction work should conform to design documents and construction procedures.

The collapse of a building is characterized as the propagation of an initial local collapse from component to component, ultimately resulting in the collapse of a whole structure or a disproportionately large portion of it.

Construction is one of the most critical phases in the life cycle of buildings due to the risk of failure and the possibility of underestimating construction loads.

The structural framework included the construction of load-bearing walls and each floor was directly stacked on the walls. Grouted bearing surfaces were used to construct the joint between the wall and the floor. This process of construction was termed system building.

Top 5 Biggest Dam Failures in the World

5 Disastrous Foundation Failures in New York City

Top 6 Energy-Efficient High-Rise Buildings in the World

Ravi Panwar

Ravi Panwar

Related posts.

Factors Influencing Earthquake Resistant Design of Structures

Factors Influencing Earthquake Resistant Design of Structures

Limit State, Working Stress and Ultimate Load Method of Structural Design

Limit State, Working Stress and Ultimate Load Method of Structural ...

Academia.edu no longer supports Internet Explorer.

To browse Academia.edu and the wider internet faster and more securely, please take a few seconds to  upgrade your browser .

Enter the email address you signed up with and we'll email you a reset link.

  • We're Hiring!
  • Help Center

paper cover thumbnail

Forensic Study and Review of Some Structural Failures -Case Studies

Profile image of raana pathak

Structural failure happens when the material of the structure is stressed to its strength limit which causes extreme deformation and fracture. Structural failure can be prevented by proper design and by studying the causes of past failures. The cause of failures helps to avoid mistakes which led to that type of failure and this mistake helps in further construction. This paper includes case studies and their causes of failures. It includes four case studies of RC and masonry building, In which one case study of truss bridge and one of cold-formed steel structure. All the structures collapse during years 2018-19.

Related Papers

International Journal of Technical Innovation in Modern Engineering & Science

ASHISH H . MAKWANA

This paper gives information about identification of risk factors and perceptions of Indian construction practitioners i.e., contractors, owners, project managers and Engineers on the importance of different construction risks and how the risks should be assigned between the different parties of the contract. As the very common project styles, construction projects have so many characteristics likewise time limitation, specific items, financial restrictions and requirements, extraordinary structural and legal situations, complexity features. For this situation every construction project has own complex method. Risks constantly happen at construction projects and frequently cause time overrun or cost overrun. If you don't contemplate these risk factors, or neglect the main factors, these risk factors will affect the damage because of the managerial errors. Risk management is the process which covers to identify the risks, for assessment with the help of qualitatively and quantitatively, to response with appropriate technique for management and controlling. The concept has gain popularity in various industries. Various companies frequently found the method in their projects for upgrading their performance, reducing their losses and increasing their profits. Questionnaire survey among clients, contractors, engineers and architects is analysed using, Relative Importance Index (RII)) method. The focus of this study is to understand what Risk Management is, understand the process of risk management at construction project and have depth knowledge on the use of risk management in high-rise construction projects.

building failure case study pdf

Procedia Engineering

Rodrigo Lopez

Subramanian Narayanan

With the dwindling natural resources, it is very important for engineers to avoid failures of any nature and build structures which are safe, stable, economic, aesthetic, durable, and environment friendly. However, building and other structural failures are occurring at regular intervals in India. These failures, though well reported in newspapers, the reasons for these collapses are not well documented, even though some committees are appointed in some cases to study the failures. If the causes of failures are well publicized, designers and builders can learn from the mistakes done by others and will not repeat them in their practice. Hence an attempt is made in this paper to describe some important failures that resulted in code clause changes or in changes to professional practice. It is high time that legislation is passed in India, similar to those available in Western Countries, such that only qualified and experienced engineers are allowed to practice, so that failures are minimized.

Forensic Science, Medicine, and Pathology

Michael Fitzpatrick , S. Hainsworth

arjunan chandrasekaran

International Journal of Technical Innovation in Modern Engineering & Science (IJTIMES)

Amitkumar D Raval

In this modern world, building structures have their own requirements in terms of design and durability. To satisfy this requirement of the structural integrity of each structure, modification of traditional cement concrete has become mandatory. plain concrete (PC) is a fragile material with low tensile strength and may crack under traction. Randomly distributed basalt fibers can bind these cracks and hinder their development. Copper smelting is an industrial by-product obtained during copper slag increase the workability of concrete. Green concrete is concrete which uses waste material as at least one of its components, which does not lead to environmental destruction or it has high performance and life cycle sustainability. This experimental work was conducted on concrete samples containing cut basalt fiber as replacement by weight of cement in concrete and copper slag as a partial replacement of a fine aggregate by copper slag at 10% 20%, 30%, 40% and 50% by weight. The standard cube measure the compressive strength after 7 days, 14 days and 28 days and water absorption test and cost compared this to that of control mixes of M25 grade.

SK.MOHAMMED ABID

The loss of catenary action in reinforced concrete structures caused due to the progressive collapse which is the collapse of all, or a large part of a structure precipitated by damage or failure of a relatively small part of it. In this project, it is proposed to carry out progressive collapse analysis of G+3 storey RC frame building with Non-Linear Dynamic Analysis on normal and varying ground slopes of hill stations, mainly 10 0 ,15 0 and 20 0 with the help of methodology mentioned in GSA 2003 guidelines. Reinforced Concrete Building consisting of 5 X 5 bay of 5 m each in both directions have been taken and designed by Indian Standard codes as a special moment resistant frame. Different Structural models of buildings on varying ground slopes have been created in finite element method based software ETABS and loads are applied as per GSA 2003 guidelines, for evaluation of progressive collapse nonlinear dynamic method of analysis has been used. To perform non-linear dynamic analysis time history data of Bhuj Earthquake has been applied to the building models. By following the guidelines of general services administration GSA 2003, such as column removal case one at a time has been carried out, namely removal of Corner column both small and long in case of varying ground slopes and Exterior column at ground floor. For all three cases, nonlinear dynamic analysis has done and DCR values are evaluated. Depending upon DCR ratios it is observed that buildings designed as per Indian standard codes are vulnerable to progressive collapse or not. Also comparison of results obtained due to non linear dynamic analysis like story displacement, base shear and story shear for both along the slope and across the slope of buildings due to effect of column removal conditions as mentioned above has been plotted.

Teja Kiran , rohini devi

The Light gauge cold-formed steel sections being used extensively in residential, industrial and commercial building as secondary load bearing members since last three decadez. In this context a study is being made to analyses C Sections with and without stiffeners to arrive at design strength criterion in compression. The direct strength method of design for cold formed steel sections has been validated over the years through research and the same has been incorporated in the standard codes of practice in the countries like USA and Australia. ABAQUS and CUFSM has been extensively used to perform Finite Element analysis and Finite Strip method of thin walled cold formed steel sections and the results are compared to each other. The analysis is being done on CUFSM and ABAQUS. The design strength curves will be arrived at using direct strength method. This is because cold-formed steel sections have a very high strength to weight ratio compared with thicker hot-rolled steel sections, and their manufacturing process is simple and cost-effective. In this context, a study is being made to analyze C sections with and without stiffeners to arrive at design strength criterion in compression members. In this study, the behavior of C sections with and without stiffeners under the action of axial loads has been carried out with various thickness and depths. In ABAQUS, the loads are applied on both ends. The clamped end conditions are considered.

Sumanth Bandaru

— Recent earthquakes in the Indian subcontinent have led to an increase in the seismic zoning factor over many parts of the country. Many existing buildings require a seismic assessment for various reasons, such as non-compliance with code requirements, code updates, poor design practices and changes in building usage. However, the existing insufficient structure can be upgraded with some rehabilitation to maintain the expected level of performance. This paper presents the seismic evaluation of the existing building of G+3 RCC structure subjected to Zone-II level earthquake forces. Building is modeled in 3D software. The existing structures are analyzed and designed as per IS 1893-1984, 1893-2002 and the design is compared as per two codal provisions also with the existing designed structural details. Retrofitting techniques are applied to the existing building for the non-compliance elements. To improve the performance of deficient members, a local retrofitting strategy is adopted. This study shows that the RCC jacketing is an efficient way to retrofit RC members to improve flexure as well as shear capacity.

RELATED PAPERS

International Journal of Technical Innovation in modern Engineering and Science- IJTIMES

Dr. Rekha Nair

kavitha venugopal

Baryalai Hajizada

VivekSheel Rajput , mudi goud

Ashish Singh Kharola

Aivaras Symanas

Himanshu Garg

Dr Chintan Pandya

Phạm Đức Thịnh

Árpád Rózsás , Miroslav Sýkora

Elias Ahmadi

VivekSheel Rajput , Sanjay Singh Pundir

Comparative Study of Monolithic Structure over Conventional Structure Monolithic Structure: A Case Study at Vadodara City

anthony Ede

SSRN Electronic Journal

Denis Binder

Engineering Failure Analysis

Jong-Kwon LIM

Repair and Rehabilitation of Structures

Julio Saire

Flavio Stochino , Maria Luisa Fadda , FAUSTO MISTRETTA

Jordan Journal of Civil Engineering

Dr Mansur Hamma-adama

Frattura Integrità Strutturale

Stamford Journal of Civil Engineering, Stamford University Press

Ali Ahmed, PhD , Md. Mahbub-ul-Alam

Analysis of Risk Categories and Factors for PPP Projects using Analytic Hierarchy Process

priyanka shende

malini malz

ESV. (Amb) O Y A N I R A N Oluwaseun Babatunde

ADENIRAN ADEDEJI

basavaraja s

Bhaskar Nuthanakanti

Engineering Structures

Vincenzo Gattulli

Civil Engineering Magazine Archive

Ronald Riggs

GRD JOURNALS , DARSHAN J MEHTA

Franco Bontempi , Konstantinos Gkoumas

Journal of Performance of Constructed Facilities

Metallurgical Design and Industry -Prehistory to the Space Age

Johana C Siliwire

Saipol Bari Abd Karim

  •   We're Hiring!
  •   Help Center
  • Find new research papers in:
  • Health Sciences
  • Earth Sciences
  • Cognitive Science
  • Mathematics
  • Computer Science
  • Academia ©2024

IMAGES

  1. (PDF) Structural Failure of Building's Walkway: Case Study

    building failure case study pdf

  2. (PDF) Retaining Wall Failure due to Poor Construction and Design

    building failure case study pdf

  3. Building failure case study

    building failure case study pdf

  4. Building failure case study

    building failure case study pdf

  5. building failure case study pdf

    building failure case study pdf

  6. building failures and causes notes and case studies bc 5th sem

    building failure case study pdf

VIDEO

  1. Structural Failure Simulation of Multi-Family House

  2. SERVICES FAILURE (CASE STUDY SERVICE MARKETING)

  3. Case study of a child बच्चे का एकल अध्ययन -B.ED /BTC

  4. Conditional Probability of Failure for Structural Systems as per ASCE

  5. structural failure

  6. 3 Big Mistakes in Slab Construction on Site

COMMENTS

  1. PDF Study of Recent Building Failures in the United States

    recent facts and trends of building failures. Failure Defined The first study by the writers, cited in the previous section, which became the foundation for this paper, discovered 65 cases of building failures that occurred between 1977 and 1981, while the second study retrieved 46 cases of building failures that took place between 1982 and 1988.

  2. Building Failure Cases

    Building Failure Cases. 2000 Commonwealth Avenue, Boston. Agricultural Product Loads. Air Force Warehouses. Bailey's Crossroads, Virginia. Bomber Crash into Empire State Building. Citicorp case study. Cleveland Lift-Slab Parking Garage. Cold-formed Steel Beam Construction Failure.

  3. PDF Building failure in South Tel Aviv: case study

    7 Conclusions. On January 2006 a residential building in the southern part of Tel Aviv failed due to large settlements of its foundations. The largest settlement of 35cm occurred at the south-east corner. As a result one of 5 sections of the building has to be demolished.

  4. (PDF) A case study of foundation failure of a residential building

    structural elements, (Car retero-Ayuso et al., 2016) conducted a statistical study based on the. analysis of damages, symptoms and their evolutions, the results of th is study showed 66% of ...

  5. Structural Failure of Building's Walkway: Case Study

    The causes of the Hyatt Regency walkway collapse was attributed to: 1. Design errors—this includes designing a walkway structure that does not meet the local code requirement, 2. Construction errors—this include verbal communications between the fabricator and the EOR, 3. Lack of design details, 4.

  6. (PDF) Causes of building failures in Africa: A case study on collapsing

    PDF | On Jan 1, 2014, Jackson Musyoka Kioko published Causes of building failures in Africa: A case study on collapsing structures in Kenya | Find, read and cite all the research you need on ...

  7. The Ronan Point Apartment Tower Case

    Introduction. In the early morning hours of May 16, 1968, the occupant of apartment 90 on the 18 th floor of the Ronan Point apartment tower lit a match for her stove to brew her morning cup of tea. The resulting gas explosion, due to a leak, knocked her unconscious. The pressure of the small gas explosion blew out the walls of her apartment ...

  8. PDF Causes of structural failures ofa building: Case study of a building at

    building: Case study of a building at Oba-Ile, Akure Received (in revised form): 25th January 2011 ... building failure were reported in Lagos State. Between January 2005 and August 2006, over eight cases of building collapse were recorded in the country. Hence, as a matter of

  9. PDF Failures Education

    number of available case history studies, which can provide insight into patterns of failure that may develop in certain types of systems or materials. Many case studies of this nature have been published in the past in the pages of STRUCTURE®. Studying past failures is particularly helpful in identifying the human component of failure,

  10. (PDF) Causes of structural failures of a building: Case study of a

    Abstract and Figures. This article investigates the cause of the failure of some parts of a two-storey building under construction, in Oba-Ile, Akure, Ondo State, Nigeria. The article examines the ...

  11. Failure Analysis of a Partially Collapsed Building using Analytical

    Building failure usually results in collapse if not discovered and properly addressed. Building collapse/failure most times causes loss of properties and lives. A case study of a partially collapsed one-story building is presented for emphasis with technical assessment of the partial-collapse cause so as to proffer remedy of the structure. This is achieved through detailed engineering analysis ...

  12. 2000 Commonwealth Avenue, Boston

    On January 25, 1971, two-thirds of a 16-story apartment building collapsed while under construction at 2000 Commonwealth Avenue, Boston, MA. Four workers died after a failure on the roof instigated a domino-like collapse all the way to the basement, where the men were found. Fortunately, the collapse took a long enough time for most of the ...

  13. 3 Important Cases of Building Collapse Due to Poor Construction

    1.1 Investigation Findings . On 2 nd March 1973, some portion of the apartment building collapsed during construction. The collapse began on the 23 rd floor when the slab of the 24 th floor was being cast. On the 23 rd floor, the slab started showing cracks and the failure of the building occurred vertically along the full height of the building, including the basement levels.

  14. Building failures : case studies in construction and design

    Building structure failures caused by defects in workmanship. S. Kobielak E. Hutnik Z. Zamiar. Engineering. 2015. The paper describes the failures caused by defects in workmanship, using the following as examples 1) the Hyatt Regency Hotel building in Kansas City, the U.S., 2) the roof over the grandstand at the….

  15. [PDF] Causes of building failures in Africa: A case study on collapsing

    This article elaborates the various causes of building failure in Africa, particularly Kenya. In addition to various causes that lead to collapse of buildings, Lack of African code of practice can also be a factor that should be put in consideration. Most codes of practice used in African countries are foreign codes either from Britain or Indian codes yet we use local materials for construction.

  16. (PDF) Structural Failure of Buildings: Issues and Challenges

    This paper discusses a list of information and issues that causes of structural failure of. buildings. Structural failure begins to occur when the material is stressed to its upper strength limit ...

  17. PDF Ee4-2 Building Envelope Failure Case Studies in High-rise Construction

    The following case studies show where the building envelope assemblies have fallen below the level of performance expected by the building occupants. The reader can decide for himself if the Standard of Care expected of reasonable and prudent building designers and developers has been breached. CASE STUDIES . Cast-In-Place Concrete Walls

  18. Building Failure

    0000000340_Building Failure- Causes and Case Studies - Free download as PDF File (.pdf), Text File (.txt) or read online for free. design of tall structure

  19. (PDF) Forensic Study and Review of Some Structural Failures -Case

    Download Free PDF. Download Free PDF. ... MS Hotel collapse and collapse of school building. Each case study (1) Sumarizes the causes of collapse; (2) Factors that lead to collapse (3) Witness review about the collapse.(4) Observations from the collapse. ... An International Journal., (2012), pp. 461 - 473. [11] P.A. Bosela, ―Use of Failure ...

  20. (PDF) Construction Project Failures Around the World: What Have We

    Effects of premature termination: Case studies of Sri Lankan construction projects. Proceeding of the Second World Construction Symposium 2013: Socio-Economic Sustainability in Construction. 14-15 ...

  21. PDF -CAUSES & CASE STUDIES

    Evidence of explosions include shattered glass, small debris of walls and crushed rubble blown to tens, even hundreds, of meters away. Secondly, the building failed suddenly and vertically. This vertical failure provoked curiosity amongst the engineers, so they investigated all the witnesses.

  22. (PDF) Geotechnical Basis for Building Instability and Failure: Case

    Geotechnical Basis for Building Instability and Failure: Case Study from Lagos, Nigeria. August 2015. DOI: 10.1007/978-3-319-09048-1_70. Authors: Ibrahim Adewuyi Oyediran. University of Ibadan ...

  23. Assessment of public building defects and maintenance ...

    This research aimed to assess building construction defects and maintenance practices in Mettu building projects. A case study and questionnaire survey were utilized for data collection. A Case ...