( ) and experts
The questionnaire was given to 22 experts and analyzed after completion by them. In this methodology, in pair-wise comparison matrix, indicators were compared two by two using codes of verbal expressions ( Table 4 ). The names of these verbal phrases and their equivalent fuzzy values are shown in Table 1 .
Response matrix of expert 1.
C1 | C2 | C3 | C4 | … | C15 | C16 | C17 | C18 | |
---|---|---|---|---|---|---|---|---|---|
C1 | 0 | H | VH | VH | … | H | L | H | VL |
C2 | H | 0 | NO | VH | … | L | L | L | H |
C3 | VH | VH | 0 | L | … | H | L | L | L |
C4 | L | L | L | 0 | … | H | L | L | L |
| | | | | | | | | | | | | | | | | | | |
C15 | H | L | VH | VL | … | 0 | VL | L | L |
C16 | H | L | L | VL | … | L | 0 | L | L |
C17 | L | L | VL | L | … | L | L | 0 | L |
C18 | L | L | VL | L | … | L | L | L | 0 |
Collecting opinions and formation of judgment matrix (ideal) was performed by using Eq. (3) ( Table 5 ), then the experts' weights were measured by using (4) , (5) , (6) , (7) . The weight of the experts is given in Table 6 .
The judgment fuzzy matrix.
C1 | C2 | C3 | … | C16 | C17 | C18 | |
---|---|---|---|---|---|---|---|
C1 | (0, 0, 0) | (4.8, 5. 9, 6.8) | (4.6, 5.8, 6.7) | … | (4.5, 5.5, 6.5) | (5.1, 6.1, 7) | (5.1, 6.1, 7) |
C2 | (5.3, 6.4, 7.3) | (0, 0, 0) | (4.1, 5.1,6) | … | (4.9, 5.9, 6.8) | (3.9, 4.9, 5.9) | (3.9, 4.8, 5.7) |
C3 | (3.5, 4.7, 5.7) | (3.6, 4.7, 5.7) | (0, 0, 0) | … | (3.2, 4.3, 5.3) | (3.4, 4.5, 5.5) | (3.3, 4.2, 5) |
| | | | | | | | | | | | | | | |
C16 | (4.5, 5.5, 6.5) | (5.1, 6.1, 7) | (5.1, 6.1, 7) | … | (0, 0, 0) | (5, 6, 7) | (3.8, 4.6, 5.2) |
C17 | (4.8, 5.9, 6.8) | (3.9, 4.9, 5.9) | (3.9, 4.8, 5.7) | … | (3.9, 5, 6.1) | (0, 0, 0) | (4, 4.9, 5.7) |
C18 | (3.2, 4.3, 5.3) | (3.4, 4.5, 5.5) | (3.3, 4.2, 5) | … | (3.9, 5, 6.1) | (3.9, 5, 6.1) | (0, 0, 0) |
Experts' weight based on milliunit.
Expert Number | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 |
Expert Weight | 37 | 36 | 35 | 36 | 36 | 36 | 36 | 36 | 36 | 36 | 36 | 35 | 35 | 35 |
Expert Number | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | 27 | 28 |
Expert Weight | 40 | 35 | 35 | 36 | 36 | 35 | 35 | 35 | 35 | 36 | 36 | 35 | 36 | 35 |
It can be concluded based on the results that the experts were also homogeneous and, the number of experts is sufficient ( Asgharpour, 2010 ).
Fuzzy Decision-making trial and evaluation laboratory technique
By applying the weight of each expert in the decision matrix by using (8) , (9) , the FDEMATEL calculations were started.
The normalized the weighted judgement fuzzy matrix.
C1 | C2 | C3 | … | C16 | C17 | C18 | |
---|---|---|---|---|---|---|---|
C1 | (0, 0, 0) | (0.04,0.05,0.06) | (0.04,0.05,0.05) | … | (0.04,0.05,0.05) | (0.18,0.22,0.25) | (0.04,0.05,0.06) |
C2 | (0.04,0.05,0.06) | (0, 0, 0) | (0.03,0.04,0.05) | … | (0.04,0.05,0.06) | (0.14,0.18,0.21) | (0.03,0.04,0.05) |
C3 | (0.03,0.04,0.05) | (0.03,0.04,0.05) | (0, 0, 0) | … | (0.03,0.04,0.04) | (0.12,0.16,0.2) | (0.03,0.03,0.04) |
| | | | | | | | | | | | | | | |
C16 | (0.04,0.05,0.05) | (0.04,0.05,0.06) | (0.03,0.04,0.05) | … | (0, 0, 0) | (0.04,0.05,0.06) | (0.03,0.04,0.04) |
C17 | (0.03,0.04,0.05) | (0.03,0.04,0.05) | (0.02,0.03,0.04) | … | (0.03,0.04,0.05) | (0, 0, 0) | (0.03,0.04,0.05) |
C18 | (0.03,0.04,0.05) | (0.03,0.04,0.05) | (0.03,0.03,0.04) | … | (0.03,0.04,0.05) | (0.03,0.04,0.05) | (0, 0, 0) |
The Total relation fuzzy matrix. (T).
C1 | C2 | C3 | … | C16 | C17 | C18 | |
---|---|---|---|---|---|---|---|
C1 | (0.07,0.17,0.6) | (0.1,0.22,0.65) | (0.1,0.2,0.61) | … | (0.1,0.22,0.66) | (0.11,0.23,0.68) | (0.11,0.22,0.65) |
C2 | (0.1,0.21,0.63) | (0.06,0.16,0.58) | (0.09,0.19,0.58) | … | (0.1,0.21,0.64) | (0.10,0.21,0.65) | (0.09,0.20,0.62) |
C3 | (0.08,0.18,0.57) | (0.08,0.18,0.57) | (0.05,0.13,0.49) | … | (0.08,0.18,0.58) | (0.08,0.19,0.59) | (0.08,0.18,0.56) |
| | | | | | | | | | | | | | | |
C16 | (0.1,0.21,0.63) | (0.10,0.21,0.63) | (0.08,0.19,0.58) | … | (0.06,0.17,0.58) | (0.11,0.22,0.65) | (0.1,0.2,0.61) |
C17 | (0.09,0.19,0.58) | (0.08,0.18,0.57) | (0.07,0.17,0.53) | … | (0.09,0.19,0.59) | (0.06,0.15,0.55) | (0.09,0.19,0.57) |
C18 | (0.09,0.19,0.58) | (0.08,0.18,0.57) | (0.07,0.17,0.54) | … | (0.09,0.19,0.59) | (0.09,0.19,0.6) | (0.06,0.15,0.53) |
Defuzzied matrix of total relation matrix numbers based on centiunit (Numbers by hundredth).
C1 | C2 | C3 | C4 | C5 | C6 | C7 | C8 | C9 | C10 | C11 | C12 | C13 | C14 | C15 | C16 | C17 | C18 | D | |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
C1 | 25 | 30 | 28 | 32 | 30 | 29 | 30 | 33 | 31 | 32 | 34 | 32 | 33 | 30 | 26 | 30 | 31 | 30 | 547 |
C2 | 29 | 24 | 26 | 30 | 30 | 27 | 29 | 31 | 30 | 30 | 33 | 31 | 32 | 29 | 25 | 29 | 29 | 28 | 522 |
C3 | 25 | 25 | 20 | 28 | 26 | 25 | 26 | 28 | 27 | 28 | 29 | 28 | 28 | 26 | 23 | 25 | 26 | 25 | 470 |
C4 | 29 | 28 | 26 | 27 | 29 | 27 | 30 | 32 | 30 | 31 | 32 | 31 | 32 | 29 | 25 | 29 | 30 | 29 | 525 |
C5 | 28 | 28 | 25 | 28 | 24 | 27 | 28 | 30 | 29 | 31 | 32 | 31 | 31 | 28 | 24 | 29 | 29 | 28 | 511 |
C6 | 29 | 29 | 28 | 31 | 29 | 23 | 29 | 31 | 30 | 30 | 33 | 30 | 31 | 28 | 26 | 29 | 30 | 29 | 526 |
C7 | 28 | 29 | 26 | 31 | 30 | 27 | 26 | 33 | 31 | 31 | 33 | 33 | 32 | 29 | 24 | 30 | 31 | 29 | 533 |
C8 | 28 | 28 | 26 | 31 | 29 | 27 | 30 | 27 | 30 | 31 | 33 | 32 | 32 | 28 | 24 | 29 | 30 | 29 | 524 |
C9 | 28 | 28 | 26 | 30 | 29 | 26 | 30 | 31 | 25 | 30 | 33 | 31 | 32 | 28 | 24 | 28 | 29 | 28 | 515 |
C10 | 28 | 28 | 26 | 30 | 30 | 27 | 29 | 31 | 30 | 26 | 33 | 31 | 32 | 30 | 25 | 29 | 30 | 29 | 522 |
C11 | 30 | 31 | 28 | 32 | 32 | 29 | 32 | 33 | 32 | 33 | 30 | 34 | 34 | 32 | 26 | 31 | 32 | 31 | 564 |
C12 | 29 | 29 | 27 | 32 | 31 | 27 | 31 | 32 | 32 | 31 | 34 | 27 | 33 | 29 | 25 | 29 | 31 | 29 | 538 |
C13 | 28 | 29 | 26 | 31 | 30 | 27 | 30 | 32 | 31 | 31 | 33 | 32 | 27 | 29 | 24 | 29 | 31 | 30 | 532 |
C14 | 27 | 27 | 25 | 28 | 28 | 26 | 28 | 29 | 28 | 30 | 31 | 29 | 30 | 23 | 24 | 27 | 28 | 27 | 495 |
C15 | 26 | 25 | 25 | 27 | 26 | 26 | 27 | 28 | 27 | 28 | 30 | 28 | 28 | 26 | 19 | 26 | 26 | 26 | 474 |
C16 | 28 | 29 | 26 | 30 | 30 | 27 | 30 | 31 | 30 | 30 | 33 | 31 | 32 | 28 | 24 | 24 | 30 | 28 | 522 |
C17 | 26 | 25 | 23 | 27 | 27 | 24 | 27 | 29 | 27 | 28 | 30 | 29 | 30 | 26 | 22 | 26 | 23 | 26 | 474 |
C18 | 26 | 26 | 24 | 27 | 27 | 24 | 27 | 29 | 27 | 28 | 29 | 29 | 30 | 26 | 22 | 26 | 27 | 22 | 476 |
R | 499 | 499 | 461 | 531 | 517 | 477 | 519 | 550 | 527 | 539 | 574 | 548 | 560 | 507 | 432 | 507 | 522 | 502 |
Arrangement of elements in different approaches of FDEMATEL technique.
C1 | C2 | C3 | C4 | C5 | C6 | C7 | C8 | C9 | |
---|---|---|---|---|---|---|---|---|---|
D + R | 1046 | 1020 | 930 | 1055 | 1028 | 1002 | 1052 | 1073 | 1042 |
D-R | 48 | 23 | 09 | 6- | 7- | 49 | 14 | 25- | 12- |
D ranking | 2 | 9 | 18 | 7 | 13 | 6 | 4 | 8 | 12 |
R ranking | 14 | 15 | 17 | 6 | 10 | 16 | 9 | 3 | 7 |
D + R ranking | 8 | 12 | 17 | 6 | 11 | 13 | 7 | 4 | 9 |
D-R ranking | 2 | 4 | 7 | 8 | 9 | 1 | 6 | 15 | 12 |
C10 | C11 | C12 | C13 | C14 | C15 | C16 | C17 | C18 | |
D + R | 1060 | 1138 | 1086 | 1092 | 1002 | 905 | 1030 | 996 | 978 |
D-R | 17- | 9- | 10- | 28- | 11- | 42 | 15 | 46- | 26- |
D ranking | 10 | 1 | 3 | 5 | 14 | 16 | 11 | 17 | 15 |
R ranking | 5 | 1 | 4 | 2 | 11 | 18 | 12 | 8 | 13 |
D + R ranking | 5 | 1 | 3 | 2 | 14 | 18 | 10 | 15 | 16 |
D-R ranking | 14 | 10 | 11 | 17 | 13 | 3 | 5 | 18 | 16 |
The assumptions of FDEMATEL technique should be applied as follow to determine the relationship between factors:
The highest sum of rows in total relation matrix (Di) shows the order of elements that have a strong impact on other elements (the factor of Leadership) ( Table 9 ).
The highest sum of the columns (Rj) represents the order of the elements influenced (the factor of Leader ship) ( Table 9 ).
The cause group has positive Di-Rj value and other factors are in the effect group. Di + Rj , represents the sum of the intensity of an element both in terms of influencing and being influenced.
Based on the FDEMATEL results, the factors of Number of stakeholders, Organizational size, Culture, Geographical dispersion, Technology, Nationality and ethnicity and Infrastructure have the positive Di-Rj value and can be classified as the cause group, and other factors are in the effect group because the Di -Rj of these factors is negative.
Number of stakeholders and Technology solve the main problem of the situation and it should be prioritized. Nationality and ethnicity is an independent factor and affects a small number of factors. Leadership is the main problem of the situation and should be solved.
The threshold value is obtained by expert judgement or the mean of the numbers in the total influence matrix ( H ) by using the (19) , (20) . The values below the threshold are of minor importance and will not be displayed.
The Final reachability matrix.
C1 | C2 | C3 | C4 | C5 | C6 | C7 | C8 | C9 | C10 | C11 | C12 | C13 | C14 | C15 | C16 | C17 | C18 | Driving Power | |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
C1 | 1 | 1 | 0 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 1 | 1 | 1 | 16 |
C2 | 1 | 1 | 0 | 1 | 1 | 0 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 1 | 1 | 0 | 14 |
C3 | 0 | 1 | 1 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 3 |
C4 | 1 | 0 | 0 | 1 | 1 | 0 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 1 | 1 | 1 | 14 |
C5 | 0 | 0 | 0 | 0 | 1 | 0 | 0 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 0 | 1 | 0 | 8 |
C6 | 1 | 1 | 0 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 1 | 1 | 0 | 14 |
C7 | 0 | 1 | 0 | 1 | 1 | 0 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 1 | 1 | 1 | 13 |
C8 | 0 | 0 | 0 | 1 | 1 | 0 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 1 | 1 | 1 | 12 |
C9 | 0 | 0 | 0 | 1 | 1 | 0 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 0 | 1 | 0 | 10 |
C10 | 0 | 0 | 0 | 1 | 1 | 0 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 1 | 1 | 1 | 13 |
C11 | 1 | 1 | 0 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 1 | 1 | 1 | 16 |
C12 | 1 | 1 | 0 | 1 | 1 | 0 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 1 | 1 | 1 | 15 |
C13 | 0 | 1 | 0 | 1 | 1 | 0 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 1 | 1 | 1 | 14 |
C14 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 1 | 0 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 0 | 0 | 6 |
C15 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | 1 | 0 | 0 | 0 | 2 |
C16 | 0 | 1 | 0 | 1 | 1 | 0 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 1 | 1 | 0 | 12 |
C17 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 1 | 1 | 1 | 0 | 0 | 0 | 1 | 0 | 4 |
C18 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 1 | 0 | 0 | 1 | 1 | 1 | 0 | 0 | 0 | 0 | 1 | 5 |
Dependency Power | 6 | 8 | 1 | 12 | 13 | 3 | 12 | 15 | 13 | 14 | 18 | 16 | 16 | 8 | 1 | 11 | 14 | 9 |
From the final reachability matrix, the number of 1 s in each matrix row is the accessible or output set (RC), and the number of 1 s in each matrix column is the predecessor or input set (AC). After determining the input and output sets, the intersection of the two sets is determined for each factor. Factors in which the output set and joint set are exactly the same are at the highest level of the hierarchy of the Interpretive Structural Model (as shown in Table 12 Figure 2 ). After the first repetition, the highest actions will be eliminated from others. And this will be repeated until the level of all factors is determined. In this study, 6 replications were performed as shown in Table 13 .
Clustering factors affecting project communications by using MICMAC analysis.
First repetition of Interpretive Structural Modeling in order to achieve Different levels of factors affecting project communications.
Factors | Output Set (RC) | Input Set (AC) | Joint Set | Level |
---|---|---|---|---|
C1 | C1C2C4C5C6C7C8C9 C10C11C12C13C14C16 C17C18 | C1C2C4C6C11C12 | C1C2C4C6C11 C12 | |
C2 | C1C2C4C5C7C8C9C10 C11C12C13C14 C16C17 | C1C2C6C7C11C12C13C16 | C1C2C7C11C12C13 C16 | |
C3 | C3C11 | C3 | C3 | |
C4 | C1C4C5C7C8C9C10C11 C12C13C14C16C17C18 | C1C2C4C6C7C8C9C10C11C12 C13 C16 | C1C4C7C8C9C10C11 C12C13C16 | |
C5 | C5C8C9C10C11C12C13 C17 | C1C2C4C5C6C7C8C9 C10C11C12C13C16 | C5C8C9C10C11C12 C13 | |
C6 | C1C2C4C5C6C7C8C9 C10C11C12C13 C16C17 | C1C6C11 | C1C6C11 | |
C7 | C2C4C5C7C8C9C10C11 C12C13C16C17C18 | C1C2C4C6C7C8C9C10C11C12 C13 C16 | C2C4C7C8C9C10C11 C12C13C16 | |
C8 | C4C5C7C8C9C10C11 C12C13C16C17 C18 | C1C2C4C5C6C7C8C9 C10C11C12C13C14C16C18 | C4C5C7C8C9C10C11 C12C13C16C18 | |
C9 | C4C5C7C8C9C10C11 C12 C13C17 | C1C2C4C5C6C7C8C9 C10C11C12C13C16 | C4C5C7C8C9C10C11 C12C13 | |
C10 | C4C5C7C8C9C10C11 C12C13C14C16 C17C18 | C1C2C4C5C6C7C8C9 C10C11C12C13C14C16 | C4C5C7C8C9C10C11 C12C13C14C16 | |
C11 | C1C2C4C5C6C7C8C9 C10C11C12C13 C14C16C17C18 | C1C2C3C4C5C6C7C8 C9C10C11C12C13C14 C15C16C17C18 | C1C2C4C5C6C7C8C9 C10C11C12C13C14C16 C17 C18 | 1 |
C12 | C1C2C4C5C7C8C9C10 C11C12C13C14 C16C17C18 | C1C2C4C5C6C7C8C9 C10C11C12C13C14C16C17C18 | C1C2C4C5C7C8C9C10 C11C12C13 C14C16C17C18 | 1 |
C13 | C2C4C5C7C8C9C10C11 C12C13C14C17C18 | C1C2C4C5C6C7C8C9 C10C11C12C13C14C16C17C18 | C2C4C5C7C8C9C10C11C12C13 C14 C17C18 | 1 |
C14 | C8C10C11C12C13C14 | C1C2C4C10C11C12 C13C14 | C10C11C12C13 C14 | |
C15 | C11C15 | C15 | C15 | |
C16 | C2C4C5C7C8C9C10C11 C12C13C16C17 | C1C2C4C6C7C8C10 C11C12C13C16 | C2C4C7C8C10C11C12 C13C16 | |
C17 | C11C12C13C17 | C1C2C4C5C6C7C8C9 C10C11C12C13C14 C16C17 | C11C12C13C17 | 1 |
C18 | C8C11C12C13C18 | C1C4C7C8C10C11C12C13C18 | C8C11C12C13 C18 | 1 |
Relation map based on FDEMATEL-ISM approach. Note: Due to the complexity of the relationship between the factors, only the relationships between each level with its next level are plotted. The relationship between the factors is shown in Table 11 .
Second to sixth repetition of Interpretive Structural Modeling to achieve different levels of factors affecting project communications.
Factors | Output Set (RC) | Input Set (AC) | Joint Set | Level |
---|---|---|---|---|
C1 | C1C2C4C5C6C7C8C9C10C14C16 | C1C2C4C6 | C1C2C4C6 | 4 |
C2 | C1C2C4C5C7C8C9C10C14 C16 | C1C2C6C7C16 | C1C2C7C16 | 5 |
C3 | C3C11 | C3 | C3 | 2 |
C4 | C1C4C5C7C8C9C10C14 C16 | C1C2C4C6C7C8C9C10C16 | C1C4C7C8C9C10 C16 | 4 |
C5 | C5C8C9C10 | C1C2C4C5C6C7C8C9C10 C16 | C5C8C9C10 | 2 |
C6 | C1C2C4C5C6C7C8C9C10C16 | C1C6 | C1C6 | 6 |
C7 | C2C4C5C7C8C9C10C16 | C1C2C4C6C7C8C9C10C16 | C2C4C7C8C9C10 C16 | 3 |
C8 | C4C5C7C8C9C10C16 | C1C2C4C5C6C7C8C9C10C14 C16 | C4C5C7C8C9C10C16 C18 | 2 |
C9 | C4C5C7C8C9C10 | C1C2C4C5C6C7C8C9C10 C16 | C4C5C7C8C9C10 | 2 |
C10 | C4C5C7C8C9C10C14C16 | C1C2C4C5C6C7C8C9C10C14 C16 | C4C5C7C8C9C10C14 C16 | 2 |
C14 | C8C10C14 | C1C2C4C10C14 | C10C11C12C13C14 | 3 |
C15 | C15 | C15 | C15 | 2 |
C16 | C2C4C5C7C8C9C10C16 | C1C2C4C6C7C8C10C16 | C2C4C7C8C10C16 | 3 |
Communication Variety (C4), Technology (C7), Communication tool (C8), Skill (C9), Participation (C10), Leadership (C11), Knowledge (C12), Levels of providing information (C13) and Infrastructure (C16) have high influence and dependency are in Linkage factors of MICMAC chart ( Figure 3 ) and have highest scores of Di , Rj so any action on these variables leads to a change in other variables. The important point is that Leadership (C11), which has the highest factor of Di + Rj , Di-Rj ( Table 10 ) and most impact on other variables.
Although the Di-Rj score of Culture (C3) and Nationality and ethnicity (C15) is positive, both the Di and Rj scores are not high enough ( Table 10 ). In addition, based on the MICMAC analysis ( Figure 3 ), this factor is located among the Autonomous factors. It is obvious that these factors are an independent factor and does not have a notable impact on other factors.
Moreover, based on the analysis of Di- Rj values in FDEMATEL, trust (C14) is listed as effect group and have tendency to be easily impacted by others (The effects in Table 11 are significant in the C14 column).
The results of MCMAC analysis ( Figure 3 ) confirm that Geographical dispersion (C6), Number of stakeholders (C1) and Organizational size (C2) are independent factors, but Technology (C7) is classified in linkage factors.
Further examination reveals that C7 is located close to the border between independent and linkage factors. As shown in Table 10 , their impact factor ( Di ) are relatively high. This factor has a high impact on other factors, and it must be properly classified as independent group.
After determining the level of all the factors affecting communications project, the results are depicted in Figure 3 . As seen in Figure 2 , Geographical dispersion at Level 6 and the Organization's size at Level 5 have the highest effect on other factors. The levels of Providing communication, Leadership, Knowledge, Information updating and Implementation of the communication plan are located at Level 1, which indicate that these factors are affected by other factors.
Based on the above results, the following recommendations are provided for implementation communication management in project:
If project managers are working in large organizations, they need to pay close attention to communication planning and complexity in order to avoid failure.
It should be noted that these findings are supported by other studies such as Steyn (2012) and Zulch (2014) , van den Hooff and de Ridder (2004) ; Hill et al. (2009) ; Čulo and Skendrovic (2010) ; Tam et al. (2011) ; Bond-Barnard et al. (2013) ; Pheng (2018) ; Hysa and Spalek (2019) ; Perumal and Bakar (2011) ; Marion et al. (2016) and Pivec and Maček (2019) .
Studies show that the number of failed projects is on the rise. Despite the fact that the number of project managers has increased significantly, what causes projects to fail? Various factors have been studied and analyzed, including the distribution of project teams and the complexity of communication networks that differ by the nature of the projects. Project managers are required to improve this process and reduce the number of failed projects, which is possible through establishing effective communication in projects. Communication planning, based on the association of effective factors with each other, really helps us establish better communication among stakeholders, especially in complex projects in different geographical regions. In fact, the establishment of a good communication strategy will specifically increase the likelihood of a successful project.
We know that each project has its own environment and conditions, and each industry has its own particular conditions to be considered. Every day, lots of information should be exchanged in projects, but the basic approach to communication requirements is essentially the same. Therefore, the informed communication strategy allows us to structure the information flow in a better and more controlled manner and to avoid the costs caused by lack of effective and timely communication. Managers should know that the budgets allocated to establishing communication are used to improve or change the most effective factors, respectively, so that they could reduce the costs of project failures as well as the costs of losing the resources and interests of the organization.
For this purpose, this study was conducted to help clarify the views of the organization's managers and project managers on project communications, and to identify factors affecting it. According to the experts' opinions, library studies and validation of factors by the experts, 18 main factors were confirmed and selected. Then, a hybrid of Fuzzy DEMATEL-ISM was used to analyze the relationships between them and presenting a structural model for them. According to the analyses, geographical dispersion has the greatest impact on factors influencing project communications. It was found by using MICMAC analysis that the number of stakeholders and size of the organization is the most important factor among factors affecting project communications. Therefore, in projects where different parts of the project are located in different geographical locations or where the number of project stakeholders is high, more attention should be paid to linkage and dependent factors associated with these factors.
The factors “information updating, implementing the communication plan, and organizational structure” are affected by linkage factors. Focus should be on the effective linkage factors including leadership, knowledge, levels of providing information, communication variety, technology, infrastructure, variety of communication tools, participation (engagement), and skills and improving them. Among these linkage factors, according to Figure 2 , communication variety is at the third level, so it has a greater impact on other factors. Next are infrastructure and technology - factors that are at the fourth level, affecting levels 5 and 6, and require more investment and attention. However, the most influential and affected factor is leadership (driving power = 16, dependency power = 18), which needs to gain the highest attention. Next are levels of information provision, knowledge, and participation (engagement), which will also require attention and care in communication planning.
However, the factors “trust, nationality, ethnicity and culture” are autonomous, meaning that they have low driving and dependency power and perhaps it is not necessary that the project manager concentrate on these factors in designing his project plan as compared to other factors.
This research can provide a new insight regarding the nature of the factor affecting the project communications in power plant, oil and gas megaprojects in Iran. Given the main logic of the method used, which is method for analyzing the system, factors that have the most impact on other factors are identified as the most important factors, and dependent factors must be considered by managers and policy makers to be improved by other factors, including the organization's policies in the geographical dispersion of different project sectors and the number of project stakeholders.
Also, special attention should be given to leadership as the highest influential (effective) and affected (influenced) factor. In order to improve leadership, it is necessary to sufficiently invest in the required skills and knowledge of project managers.
Project communication has a great influence on the success of the project. Considerable consideration and investment should be given to the factors affecting project communications and their effects on each other in order to have a positive impact on project communications and project success. Enhanced knowledge of project managers on the effect of these factors during project communications planning can be very efficient and prevent the loss of time and cost. Since no importance weights were obtained for the factors in this study, it is suggested that a combination of this method with a weighting method like Analytic Network Process (ANP) or weighting with prioritization like DANP method, etc. be used.
We can also examine the structural relations of the present model with Structural Equation Modeling (SEM) technique. It should be noted that the implementation of each of the factors is likely to have many barriers and conflicts. Researchers can investigate these problems in future studies. The first limitation that can be stated is the number of criteria that can be greater than this number and also the results should be evaluated using larger samples across a variety of organizations and countries.
Author contribution statement.
M. Khalilzadeh: Conceived and designed the experiments; Performed the experiments; Analyzed and interpreted the data.
H. Shakeri: Contributed reagents, materials, analysis tools or data; Wrote the paper.
This research did not receive any specific grant from funding agencies in the public, commercial, or not-for-profit sectors.
The authors declare no conflict of interest.
No additional information is available for this paper.
Accessibility Links
Click here to close this panel.
Purpose-led Publishing is a coalition of three not-for-profit publishers in the field of physical sciences: AIP Publishing, the American Physical Society and IOP Publishing.
Together, as publishers that will always put purpose above profit, we have defined a set of industry standards that underpin high-quality, ethical scholarly communications.
We are proudly declaring that science is our only shareholder.
F Y Hernández 1 , R P Ramírez 1 and R I Laguado 1
Published under licence by IOP Publishing Ltd Journal of Physics: Conference Series , Volume 1388 , 5th International Week of Science, Technology & Innovation 20 November 2018, San José de Cúcuta, Colombia Citation F Y Hernández et al 2019 J. Phys.: Conf. Ser. 1388 012048 DOI 10.1088/1742-6596/1388/1/012048
5103 Total downloads
Author e-mails.
1 Grupo de Investigación en Innovación y Gestión Productiva GIINGPRO, Universidad Francisco de Paula Santander, San José de Cúcuta, Colombia
Buy this article in print
The communication project is a key factor to achieve good results in the development of a project; this includes the processes of planning, collecting, creating, storing, controlling and distributing information in a timely manner. In this context, the general objective of the research was to evaluate the communications management for the success of projects in a provincial university. In the first instance, communications assessment at the institutional level is carried out, the type of requirements and the use of communication methods are determined and then a communications plan is proposed. The type of research is descriptive, where a series of variables are selected, each of them are measured independently in order to describe them. As a result of the research, those involved in carrying out the projects were identified, it was obtained that the management of communications ensures a better distribution of information at all levels of the institution, in addition, the design of the communications plan allows the information to be transmitted efficiently and assertively.
Export citation and abstract BibTeX RIS
Content from this work may be used under the terms of the Creative Commons Attribution 3.0 licence . Any further distribution of this work must maintain attribution to the author(s) and the title of the work, journal citation and DOI.
Project management has become an essential skill for organizations to achieve their goals efficiently. By effectively managing projects, businesses can streamline processes, improve productivity, and ultimately drive success. To understand the intricacies of project management, it is crucial to explore various case studies that offer real-life insights into successful project management practices. This comprehensive guide aims to provide a deep dive into project management, highlighting key principles, methodologies, and the role of a project manager.
Project management is a crucial discipline that involves the application of knowledge, skills, tools, and techniques to project activities. Its primary goal is to meet specific project requirements by carefully planning, executing, controlling, and closing projects within defined constraints. These constraints typically include factors such as time, cost, and scope. By effectively managing these elements, project managers aim to achieve predetermined objectives while ensuring efficient resource utilization.
At its core, project management is a multifaceted process that requires a comprehensive understanding of various project elements. It encompasses the coordination of tasks, resources, and stakeholders to achieve project goals. By employing proven methodologies and strategies , project managers can effectively navigate the complexities of project execution.
Successful project management involves breaking down complex projects into manageable tasks, establishing clear project objectives, and developing a well-defined project plan . This plan serves as a roadmap for the project, outlining the necessary steps, timelines, and deliverables. By having a solid plan in place, project managers can effectively allocate resources, manage risks, and monitor progress throughout the project lifecycle.
Project management is guided by a set of key principles that serve as the foundation for successful project execution. These principles include:
A project manager plays a pivotal role in the success of any project. They are responsible for planning, organizing, and overseeing all project activities. Key responsibilities of a project manager include:
By fulfilling these roles and responsibilities, project managers act as leaders, decision-makers, and facilitators. They work closely with stakeholders to ensure that project goals are met, deliverables are achieved, and project outcomes align with organizational objectives.
Project management plays a crucial role in the success of organizations. It is a discipline that involves planning, organizing, and controlling resources to achieve specific goals and objectives. Effective project management ensures that projects are executed efficiently, meeting the desired outcomes while staying within the allocated budget and time frame.
Effective project management offers numerous benefits to organizations. Firstly, it enhances collaboration among team members. By establishing clear roles and responsibilities, project managers facilitate effective communication and coordination, ensuring that everyone is working towards a common goal. This collaboration fosters innovation, creativity, and synergy among team members, leading to higher productivity and better outcomes.
Furthermore, effective project management promotes efficient resource allocation . Project managers carefully analyze the project requirements and allocate resources, such as manpower, equipment, and materials, in the most optimal way. This ensures that resources are utilized effectively, minimizing waste and maximizing productivity. By efficiently managing resources, organizations can achieve cost savings and improve their overall operational efficiency.
In addition, effective project management minimizes risks. Project managers identify potential risks and develop strategies to mitigate them. They create contingency plans and establish risk management processes to address any unforeseen events or challenges that may arise during the project. By proactively managing risks, organizations can minimize disruptions, avoid costly mistakes, and ensure the successful completion of projects.
Moreover, effective project management enables effective decision-making. Project managers gather relevant data, analyze information, and make informed decisions based on the project’s objectives and constraints. They consider various factors, such as cost, quality, and time, to make decisions that align with the organization’s overall strategy. This ensures that projects are executed in a way that maximizes value and achieves the desired outcomes.
Lastly, effective project management ensures projects are completed on time and within budget. Project managers develop detailed project plans, set realistic timelines, and monitor progress to ensure that projects stay on track . They closely monitor project costs and implement cost control measures to prevent budget overruns. By delivering projects on time and within budget, organizations can enhance customer satisfaction, build trust, and maintain a competitive edge in the market.
Scope creep.
On the other hand, poor project management can have severe consequences for organizations. When project management is not effectively implemented, it can result in scope creep. Scope creep refers to the continuous expansion of project requirements beyond the initial scope, leading to increased costs, delays, and a loss of focus. This can strain relationships with stakeholders, as their expectations may not be met, and can ultimately lead to project failure.
Poor project management can also result in budget overruns. Without proper planning and control, projects can exceed their allocated budgets, causing financial strain on the organization. This can lead to reduced profitability, cash flow issues, and potential financial losses. Additionally, budget overruns can negatively impact the organization’s reputation, as stakeholders may view the organization as inefficient or unreliable.
Missed deadlines are another consequence of poor project management. When projects are not effectively managed, timelines may not be realistic or properly monitored. This can lead to delays in project completion, causing frustration among stakeholders and potentially impacting the organization’s ability to deliver products or services on time. Missed deadlines can also result in missed business opportunities, as competitors may gain an advantage by delivering similar projects more efficiently.
Furthermore, poor project management can strain relationships with stakeholders. When projects are not effectively communicated or managed, stakeholders may feel excluded or uninformed. This can lead to misunderstandings, conflicts, and a lack of trust in the organization’s ability to execute projects successfully. Strained relationships can have long-term consequences, as stakeholders may choose to disengage from future projects or seek alternative partnerships.
Ultimately, failed projects can damage a company’s reputation. When projects fail to meet their objectives, it can erode customer confidence and trust in the organization’s ability to deliver on its promises. This can result in a loss of business opportunities, as potential customers may choose to work with competitors who have a track record of successful project execution. Additionally, failed projects can demoralize employees and create a negative work environment, impacting overall organizational performance.
In conclusion, effective project management is vital for organizations to achieve their goals and objectives. It offers numerous benefits, including enhanced collaboration, efficient resource allocation, risk mitigation, effective decision-making, and timely project completion. On the other hand, poor project management can have severe consequences, such as scope creep, budget overruns, missed deadlines, strained relationships, and damage to the organization’s reputation. Therefore, organizations should prioritize investing in project management practices and ensure they have skilled project managers who can effectively lead and execute projects.
Initiation phase.
In the initiation phase, project managers work closely with stakeholders to define project objectives and analyze feasibility. This phase involves identifying the project scope, clarifying deliverables, and assembling the project team. It sets the stage for the successful execution of the project.
The planning phase is a critical stage where project managers develop a detailed roadmap for project execution. It involves defining project activities, estimating resources and timelines, identifying risks, and developing contingency plans. Effective planning ensures all project stakeholders have a clear understanding of project requirements and paves the way for seamless execution.
In the execution phase, project plans are put into action. Project managers coordinate and oversee the project team, allocate resources, and monitor progress. Effective communication and collaboration are crucial during this phase to address any issues that may arise and keep the project on track.
The closure phase signifies the completion of the project. Project managers conduct a final review to ensure all deliverables have been met, obtain stakeholder feedback, and document lessons learned. This phase allows organizations to celebrate successes, evaluate performance, and gather valuable insights for future projects.
Waterfall methodology.
The waterfall methodology is a linear approach to project management, where tasks are completed sequentially. It involves distinct phases, with one phase starting only after the previous one is finished. This methodology is ideal for projects with well-defined requirements and limited changes expected throughout the project lifecycle.
The agile methodology is an iterative and flexible approach to project management. It emphasizes adaptability, collaboration, and continuous improvement. Agile projects are divided into short iterations called sprints, with frequent feedback loops, allowing for rapid adjustments and enhancements as the project progresses.
The hybrid methodology combines elements of both waterfall and agile methodologies. It allows project managers to tailor their approach based on project requirements and complexity. A hybrid approach offers the flexibility of agile methodologies while still incorporating structured planning and control from the waterfall model.
By delving into project management case studies, we can uncover valuable insights and lessons from successful projects. Understanding the basics of project management, recognizing its importance, and following established processes and methodologies sets the stage for achieving project goals efficiently. Whether you choose a traditional waterfall approach, an agile methodology, or a hybrid model, the key to project management success lies in effective leadership, collaboration, and adaptability.
Project management software for small teams like yours.
Small teams do big things when they’re organized.
The future of team collaboration.
Teamhub is made for your entire organization. Collaborate across departments and teams.
Create private projects or docs inside public Hubs. The structure of every Hub can be as unique as your organization.
Get a high level view of everything in your team, department and organization
Invite your clients and contractors and collaborate on projects together.
See your tasks and work the way you prefer. Create views custom to your team.
Use pre-made project templates to save time and get you started.
Powerful time-off management capabilities. Employee directories, attachments, leave management and onboarding.
Human resources, what makes us great.
The magic that sets us apart from everyone else
One price for access to all our apps. Save a ton in SaaS costs.
Assign tasks and be alerted right away if team members are away.
Map out your business processes. Take the thinking out of flows.
Your personal space, visible only to those you invite in.
Organize each hub or folders to your own preference.
Set up triggers for dozens of different actions and reduce manual effort.
Adding {{itemName}} to cart
Added {{itemName}} to cart
Department of Engineering, Hofstra University, Hempstead, USA
This alert has been successfully added and will be sent to:
You will be notified whenever a record that you have chosen has been cited.
To manage your alert preferences, click on the button below.
Please log in to your account
This paper evaluates the effectiveness of using strategic approaches for managing communication in projects, especially for top-level managers and lower-level employees. The gap of communication could be resolved by implementing strategic approaches of communication management, so as to include all personnel in the organization. According to Neves and Eisenberger (2012), the literature of communication management has stated that it is a key factor for success. Furthermore, Ramsing (2009) claimed that in recent years, most project managers have different educational backgrounds, but they also have limited backgrounds in communication management. To overcome this problem, the authors will state the most effective strategies for managers to utilize for communication in a project. They believe that the there are four most effective strategies, which are the PMI communication strategy, the six main steps of communication strategy, understanding the direction of communication, and choosing the right communication channel.
Human-centered computing
Social and professional topics
Professional topics
Computing and business
Management of computing and information systems
Project and people management
Project management techniques
Project staffing
Software and its engineering
Software creation and management
Collaboration in software development
Programming teams
Rethinking communication in it project management.
This paper is a response to the call in the Rethinking Project Management (RPM) study for new ways of thinking regarding project management. In particular, this paper presents a critique of existing thinking on communication in project management, and ...
Project management theory and practice can contribute to crisis management. As a source of essential knowledge in management, it can be used to explain principles of crisis management to professionals who understand project management. A manager ...
The resource-based view of the firm from strategic management literature is applied to examine project management as a source of competitive advantage. In this view, assets contribute to competitive advantage if they add economic value, are rare, are ...
Check if you have access through your login credentials or your institution to get full access on this article.
Copyright © 2020
United States
Other metrics.
This publication has not been cited yet
View this article in digital edition.
https://dl.acm.org/doi/10.4018/IJAL.2020070105
We are preparing your search results for download ...
We will inform you here when the file is ready.
Your file of search results citations is now ready.
Your search export query has expired. Please try again.
An online, peer-reviewed, open access journal.
Case Studies in Strategic Communication (CSSC) is dedicated to the study of strategic communication through the case study form. Case studies illustrate the strategies, tactics, and execution of communication campaigns through in-depth coverage of a single situation. CSSC is a peer-reviewed online publication housed at the University of Southern California’s Annenberg School for Communication & Journalism.
Case studies have long been central to the study of strategic communication, but these cases have been scattered across textbooks and websites, are quickly outdated, are not fully representative of the many facets of strategic communication, and lack a common format useful for teachers and scholars. Through the ongoing publication of strategic communication case studies online, CSSC aims to develop a living resource of diverse case materials for teachers, scholars, and practitioners.
As technological convergence and industry trends demand the integration of several branches of strategic communication in everyday practice, it is necessary to consider the approach to strategic communication holistically. Thus, CSSC welcomes case studies dealing with any number of the following disciplines: public relations, marketing, advertising, integrated marketing communication, social media campaigns, crisis communication, special events planning, development and fundraising, internal or employee communication, investor relations, community relations, media relations, online community management, publicity, and more.
There is no limit to topical coverage, and CSSC hopes to develop a resource that touches on as many industries, tactics, geographic regions, and diverse populations as possible. CSSC seeks case studies concerning all sectors, too: private companies (large and small), publicly traded corporations, non-profit organizations (large and small), political campaigns, government agencies (local and national), and educational institutions.
In addition to success stories, CSSC also seeks case studies that explore failures, shortcomings, missed opportunities, and crises. Stories of failure are not often told in case study collections, but they sometimes yield the best lessons.
CSSC was launched in 2011 at the University of North Carolina School of Journalism & Mass Communication, began publishing case studies in 2012, and moved to USC Annenberg in 2013.
USC Annenberg Press is committed to excellence in communication scholarship, journalism, media research, and application. To advance this goal, we edit and publish prominent scholarly publications that are both innovative and influential, and that chart new courses in their respective fields of study. Annenberg Press is among the first to deliver journal content online free of charge, and devoted to the wide dissemination of its content. Annenberg Press continues to offer scholars and readers a forum that meets the highest standards of peer review and engages established and emerging scholars from anywhere in the world.
Want to create or adapt books like this? Learn more about how Pressbooks supports open publishing practices.
1. WHAT IS TECHNICAL COMMUNICATION?
No one knows exactly how much poor communication costs business, industry and government each year, but estimates suggest billions. In fact, a recent estimate claims that the cost in the U.S. alone are close to $4 billion annually! [1] Poorly-worded or inefficient emails, careless reading or listening to instructions, documents that go unread due to poor design, hastily presenting inaccurate information, sloppy proofreading — all of these examples result in inevitable costs. The problem is that these costs aren’t usually included on the corporate balance sheet at the end of each year; if they are not properly or clearly defined, the problems remain unsolved.
You may have seen the Project Management Tree Cartoon before ( Figure 1.4.1 ); it has been used and adapted widely to illustrate the perils of poor communication during a project.
The waste caused by imprecisely worded regulations or instructions, confusing emails, long-winded memos, ambiguously written contracts, and other examples of poor communication is not as easily identified as the losses caused by a bridge collapse or a flood. But the losses are just as real—in reduced productivity, inefficiency, and lost business. In more personal terms, the losses are measured in wasted time, work, money, and ultimately, professional recognition. In extreme cases, losses can be measured in property damage, injuries, and even deaths.
The following “case studies” show how poor communications can have real world costs and consequences. For example, consider the “ Comma Quirk ” in the Rogers Contract that cost $2 million. [3] A small error in spelling a company name cost £8.8 million. [4] Examine Edward Tufte’s discussion of the failed PowerPoint presentation that attempted to prevent the Columbia Space Shuttle disaster. [5] The failure of project managers and engineers to communicate effectively resulted in the deadly Hyatt Regency walkway collapse. [6] The case studies below offer a few more examples that might be less extreme, but much more common.
In small groups, examine each “case” and determine the following:
Present your findings in a brief, informal presentation to the class.
Exercises adapted from T.M Georges’ Analytical Writing for Science and Technology. [7]
CASE 1: The promising chemist who buried his results
Bruce, a research chemist for a major petro-chemical company, wrote a dense report about some new compounds he had synthesized in the laboratory from oil-refining by-products. The bulk of the report consisted of tables listing their chemical and physical properties, diagrams of their molecular structure, chemical formulas and data from toxicity tests. Buried at the end of the report was a casual speculation that one of the compounds might be a particularly safe and effective insecticide.
Seven years later, the same oil company launched a major research program to find more effective but environmentally safe insecticides. After six months of research, someone uncovered Bruce’s report and his toxicity tests. A few hours of further testing confirmed that one of Bruce’s compounds was the safe, economical insecticide they had been looking for.
Bruce had since left the company, because he felt that the importance of his research was not being appreciated.
CASE 2: The rejected current regulator proposal
The Acme Electric Company worked day and night to develop a new current regulator designed to cut the electric power consumption in aluminum plants by 35%. They knew that, although the competition was fierce, their regulator could be produced more affordably, was more reliable, and worked more efficiently than the competitors’ products.
The owner, eager to capture the market, personally but somewhat hastily put together a 120-page proposal to the three major aluminum manufacturers, recommending that the new Acme regulators be installed at all company plants.
She devoted the first 87 pages of the proposal to the mathematical theory and engineering design behind his new regulator, and the next 32 to descriptions of the new assembly line she planned to set up to produce regulators quickly. Buried in an appendix were the test results that compared her regulator’s performance with present models, and a poorly drawn graph showed the potential cost savings over 3 years.
The proposals did not receive any response. Acme Electric didn’t get the contracts, despite having the best product. Six months later, the company filed for bankruptcy.
CASE 3: The instruction manual the scared customers away
As one of the first to enter the field of office automation, Sagatec Software, Inc. had built a reputation for designing high-quality and user-friendly database and accounting programs for business and industry. When they decided to enter the word-processing market, their engineers designed an effective, versatile, and powerful program that Sagatec felt sure would outperform any competitor.
To be sure that their new word-processing program was accurately documented, Sagatec asked the senior program designer to supervise writing the instruction manual. The result was a thorough, accurate and precise description of every detail of the program’s operation.
When Sagatec began marketing its new word processor, cries for help flooded in from office workers who were so confused by the massive manual that they couldn’t even find out how to get started. Then several business journals reviewed the program and judged it “too complicated” and “difficult to learn.” After an impressive start, sales of the new word processing program plummeted.
Sagatec eventually put out a new, clearly written training guide that led new users step by step through introductory exercises and told them how to find commands quickly. But the rewrite cost Sagatec $350,000, a year’s lead in the market, and its reputation for producing easy-to-use business software.
CASE 4: One garbled memo – 26 baffled phone calls
Joanne supervised 36 professionals in 6 city libraries. To cut the costs of unnecessary overtime, she issued this one-sentence memo to her staff:
After the 36 copies were sent out, Joanne’s office received 26 phone calls asking what the memo meant. What the 10 people who didn’t call about the memo thought is uncertain. It took a week to clarify the new policy.
CASE 5: Big science — Little rhetoric
The following excerpt is from Carl Sagan’s book, The Demon-Haunted World: Science as a Candle in the Dark, [8] itself both a plea for and an excellent example of clear scientific communication:
The Superconducting Supercollider (SSC) would have been the preeminent instrument on the planet for probing the fine structure of matter and the nature of the early Universe. Its price tag was $10 to $15 billion. It was cancelled by Congress in 1993 after about $2 billion had been spent — a worst of both worlds outcome. But this debate was not, I think, mainly about declining interest in the support of science. Few in Congress understood what modern high-energy accelerators are for. They are not for weapons. They have no practical applications. They are for something that is, worrisomely from the point of view of many, called “the theory of everything.” Explanations that involve entities called quarks, charm, flavor, color, etc., sound as if physicists are being cute. The whole thing has an aura, in the view of at least some Congresspeople I’ve talked to, of “nerds gone wild” — which I suppose is an uncharitable way of describing curiosity-based science. No one asked to pay for this had the foggiest idea of what a Higgs boson is. I’ve read some of the material intended to justify the SSC. At the very end, some of it wasn’t too bad, but there was nothing that really addressed what the project was about on a level accessible to bright but skeptical non-physicists. If physicists are asking for 10 or 15 billion dollars to build a machine that has no practical value, at the very least they should make an extremely serious effort, with dazzling graphics, metaphors, and capable use of the English language, to justify their proposal. More than financial mismanagement, budgetary constraints, and political incompetence, I think this is the key to the failure of the SSC.
CASE 6: The co-op student who mixed up genres
Chris was simultaneously enrolled in a university writing course and working as a co-op student at the Widget Manufacturing plant. As part of his co-op work experience, Chris shadowed his supervisor/mentor on a safety inspection of the plant, and was asked to write up the results of the inspection in a compliance memo . In the same week, Chris’s writing instructor assigned the class to write a narrative essay based on some personal experience. Chris, trying to be efficient, thought that the plant visit experience could provide the basis for his essay assignment as well.
He wrote the essay first, because he was used to writing essays and was pretty good at it. He had never even seen a compliance memo, much less written one, so was not as confident about that task. He began the essay like this:
On June 1, 2018, I conducted a safety audit of the Widget Manufacturing plant in New City. The purpose of the audit was to ensure that all processes and activities in the plant adhere to safety and handling rules and policies outlined in the Workplace Safety Handbook and relevant government regulations. I was escorted on a 3-hour tour of the facility by…
Chris finished the essay and submitted it to his writing instructor. He then revised the essay slightly, keeping the introduction the same, and submitted it to his co-op supervisor. He “aced” the essay, getting an A grade, but his supervisor told him that the report was unacceptable and would have to be rewritten – especially the beginning, which should have clearly indicated whether or not the plant was in compliance with safety regulations. Chris was aghast! He had never heard of putting the “conclusion” at the beginning . He missed the company softball game that Saturday so he could rewrite the report to the satisfaction of his supervisor.
Technical Writing Essentials Copyright © 2019 by Suzan Last is licensed under a Creative Commons Attribution 4.0 International License , except where otherwise noted.
Implement a public leadership approach for long-term success..
Join Harvard Kennedy School faculty and former Pentagon Chief of Staff Eric Rosenbach to learn how to develop strategies for public leadership success.
How do you execute a strategic initiative that has a long-lasting impact? Do you know how to effectively communicate your strategic approach, gathering input and support from key stakeholders? How will you anticipate and respond to scrutiny from shareholders, news media, and the public?
Leaders in government, non-profit, and education organizations face unique challenges when it comes to making strategic, business-oriented decisions. If not thoroughly planned and executed, these decisions have real consequences with high-stakes outcomes. What can we learn from world leaders and experts who have faced these monumental decisions? How can you build a high performing team to successfully execute strategic ideas?
In Strategy Execution for Public Leadership, former United States Pentagon Chief of Staff and Assistant Secretary of Defense for Homeland Defense and Global Security Eric Rosenbach will lead you through real-life public sector challenges, showing you how a purpose-driven strategy execution framework can lead to long-term adoption and success.
This government and nonprofit leadership training online course offers the opportunity to study decisions of key public leaders, like Former United States Secretary of Defense Ash Carter, so you can better understand how to develop strategies that not only align with your organizational goals, but also gain insight into the challenges and scrutiny that come along with making public decisions. Too often, public strategies fail because leaders don’t think about execution, which is made up of leadership and management tools, as well as a team who anticipates all scenarios prior to putting your plan into place.
Through global case studies and protagonist examples, you will explore topics that set you on a path to strengthen your public leadership skills, including leadership and team development, resource and budget planning, talent recruitment and retention, strategic communications and crisis management, and risk planning and mitigation tactics.
By the end of this leadership development course, you will not only have the tools to create a sound public strategy, but also know how to test and optimize your strategy, increase competitive advantage, and sustain long-term impact and success.
Strategy is not one-size-fits-all. Implement a public leadership approach for long-term success.
The course will be delivered via HBS Online’s course platform and immerse learners in real-world examples from experts at industry-leading organizations. By the end of the course, participants will be able to:
Eric Rosenbach is a Senior Lecturer in Public Policy and is the Director of the Defense, Emerging Technology, and Strategy Program at the Belfer Center for Science and International Affairs. Rosenbach teaches graduate courses in policy development, strategy execution, and national security. As Pentagon Chief of Staff from 2015–2017, Rosenbach led and managed the execution of dozens of high-profile strategic initiatives for the largest public sector organization in the world. As Assistant Secretary of Defense, Rosenbach was responsible for developing and executing the strategy for all aspects of the Department’s cyber activities and other key areas of defense policy. In the private sector, he led the cybersecurity practice of a global management consulting firm, advising the executives of Fortune 500 companies on strategic risk mitigation strategies.
Affiliations are listed for identification purposes only.
Leadership is a valuable skill that can be cultivated and strengthened. Hear from the Executive Director of The American Civil Liberties Union of Texas to discover what it takes to become an effective leader at any level.
Communication errors are often cited as the primary reason that initiatives fail. Learn the best strategies for effective communications and media relations from a former United States Secretary of Defense.
Risk prevention and mitigation is everyone’s responsibility. Explore how to assess and mitigate risks by learning about international events, including the Ebola Endemic, BP Oil Spill, and more.
Past participant discounts.
Learners who have enrolled in at least one qualifying Harvard Online program hosted on the HBS Online platform are eligible to receive a 30% discount on this course, regardless of completion or certificate status in the first purchased program. Past Participant Discounts are automatically applied to the Program Fee upon time of payment. Learn more here .
Learners who have earned a verified certificate for a HarvardX course hosted on the edX platform are eligible to receive a 30% discount on this course using a discount code. Discounts are not available after you've submitted payment, so if you think you are eligible for a discount on a registration, please check your email for a code or contact us .
For this course we offer a 30% discount for learners who work in the nonprofit, government, military, or education fields.
Eligibility is determined by a prospective learner’s email address, ending in .org, .gov, .mil, or .edu. Interested learners can apply below for the discount and, if eligible, will receive a promo code to enter when completing payment information to enroll in a Harvard Online program. Click here to apply for these discounts.
Gather your team to experience Strategy Execution for Public Leadership and other Harvard Online courses to enjoy the benefits of learning together:
Learn more and enroll your team !
Local, state, and national government leaders will benefit by better understanding the core principles of public sector strategy formulation and execution.
Military, defense, local, state, and federal officials, learn the the business fundamentals of strategy, including competitive analysis, stakeholder identification, and feedback.
Focused on rising leaders who will benefit from understanding how public sector strategy and execution serves a unique purpose, and can serve as the eyes and ears on the ground to enhance adoption and strategy optimization.
“My goal for taking the course was to better understand public program decision making. The course was thoughtfully developed and gave me the opportunity to better understand the public leadership perspective. I would recommend this course to individuals wanting a career in public leadership.”
Rob Arnold Executive Director Health Commons Project
This public leadership training course will help executives, managers, and rising managers in the nonprofit, government, and education sectors develop and implement actionable plans and strategies that will have a lasting impact on their organizations and communities they serve.
Online Course requirements: There are no prerequisites needed to take this online course. In order to earn a Certificate of Completion from Harvard Online, participants must thoughtfully complete all 8 modules, including satisfactory completion of the associated quizzes, by stated deadlines.
Download Full Syllabus
Download November 2023 Calendar
Download February 2024 Calendar
Enroll today in Harvard Online's Strategy Execution for Public Leadership course.
What are the learning requirements? How do I list my certificate on my resume? Learn the answers to these and more in our FAQs.
Data privacy and technology.
Explore legal and ethical implications of one’s personal data, the risks and rewards of data collection and surveillance, and the needs for policy, advocacy, and privacy monitoring.
Open innovation is a strategy that suggests the best ideas, solutions, and people necessary to solve your organization’s difficult problems may come from outside your company entirely.
How do you govern a country as large, diverse, and complex as the United States? Find out in this course taught by Harvard Professor Thomas E. Patterson. .
Current issue, trolling and sick burns john fetterman’s winning social media strategy against mehmet oz in the 2022 pennsylvania senate campaign.
Project management case study analyses showcase and compare real-life project management processes and systems scenarios. These studies shed light on the common challenges that project managers encounter on a daily basis. This helps project managers develop effective strategies, overcome obstacles, and achieve successful results.
By leveraging project management case studies , organisations can optimise their operations by providing insights into the most effective approaches. With effective implementation of these case studies, strategies, and methodologies, ensuring successful project completion is achievable.
The top 20 case studies are selected based on significance, impact, challenges, project management strategies, and overall success. They provide diverse insights and lessons for project managers and organisations.
1. The Sydney Opera House Project
The Sydney Opera House Project is an iconic example of project management case studies as it faced multiple challenges during its construction phase. Despite facing leadership changes, budget overruns, and design failures, the project persevered and was completed in 1973, a decade later than planned. The Opera House stands as a symbol of perseverance and successful project management in the face of humankind.
2. The Airbus A380 Project
The Airbus A380 Project is a project management case study showcasing the challenges encountered during developing and producing the world’s largest commercial aircraft. The project experienced massive delays and impacted costs of more than $6 billion, with several issues arising from the manufacturing and delivery process, outsourcing, and project coordination.
However, the Airbus A380 was successfully launched through carefully planned project management strategies, delivering a world-class aircraft that met customer expectations.
3. The Panama Canal Expansion Project
The Panama Canal Expansion Project serves as a compelling case study, illustrating the management’s encounters in expanding the capacity of the Panama Canal. The project included multiple stakeholders, technological innovations, environmental concerns, and safety challenges.
4. The Boston Central Artery/Tunnel Project
The Boston Central Artery/Tunnel Project serves as a project management case study of a large-scale underground tunnel construction project. It successfully addressed traffic congestion and was completed in 2007. The project was completed in 2007, with numerous hurdles delaying progress like complexity, technology failure, ballooning budgets, media scrutiny, etc.
5. The London 2012 Olympics Project
The London 2012 Olympics Project stands as a successful project management case study, showcasing the management of a large-scale international sporting event. This project involved the construction of a new sports infrastructure, event logistics and security concerns. The project was successfully accomplished, delivering a world-class event that captivated the audience.
6. The Hoover Dam Bypass Project
The Hoover Dam Bypass Project was a construction project in the United States of America that intended to alleviate traffic from the Hoover Dam by building a new bridge. Completed in 2010, the bridge spans across the Colorado River, connecting Arizona and Nevada and offers a safer and more efficient route for motorists.
7. The Golden Gate Bridge Seismic Retrofit Project
The Golden Gate Bridge Seismic Retrofit Project is a case study example constructed in San Francisco, California. Its objective was to enhance the bridge’s resilience against earthquakes and aftershocks. Completed in 2012, the project included the installation of shock absorbers and other seismic upgrades to ensure the bridge’s safety and functionality in the event of a major earthquake.
8. The Hong Kong-Zhuhai-Macau Bridge Project
The Hong Kong-Zhuhai-Macau Bridge Project is a massive case study that intends to connect Hong Kong, Zhuhai and Macau with a bridge-tunnel system of 55 kilometres. Completed in 2018, the project required massive funds, investments and innovative engineering solutions, providing a new transport link and boosting regional connectivity.
Check out our free courses and upskill yourself.
9. The Panama Papers Investigation Project
The Panama Papers Investigation Project is a global case study of journalistic investigations into offshore tax havens. It involved leaked documents from Mossack Fonseca, a Panamanian law firm. Coordinated by the International Consortium of Investigative Journalists, the project resulted in major political and financial repercussions worldwide, garnering widespread media attention.
10. The Apple iPhone Development Project
The Apple iPhone Development Project started in 2004, aiming to create a groundbreaking mobile device. In 2007, the iPhone transformed the industry with its innovative touchscreen interface, sleek design, and advanced features. This project involved significant research, development, marketing, and supply chain management investments.
Learn Management Courses from the World’s top Universities. Earn Masters, Executive PGP, or Advanced Certificate Programs to fast-track your career.
11. The Ford Pinto Design and Launch Project
The Ford Pinto Design and Launch Project was a developmental project intended to create an affordable, fuel-efficient subcompact car. Launched in 1971, because of its fuel tank design, it became infamous for safety issues. The project was rigged for ethical and safety concerns, lawsuits, and recalls.
12. The Deepwater Horizon Oil Spill Response Project
The Deepwater Horizon Oil Spill Response Project was a response to the largest oil spill in US history, caused by an offshore drilling rig explosion in 2010. This crisis response project utilised a waterfall project management approach, where the project team followed a pattern of planning, executing, monitoring, and closing phases.
13. The NASA Challenger Space Shuttle Disaster Project
The NASA Challenger Disaster Project was a tragic space exploration mission in 1986, resulting in the loss of all seven crew members. Extensive investigations revealed design and safety flaws as the cause. This disaster prompted NASA to address decision-making processes and improve safety cultures.
14. The Three Gorges Dam Project
The Three Gorges Dam Project was a large-scale infrastructure project developed in China that aimed to build the world’s largest hydroelectric dam on the Yangtze River. Completed in 2012, it encountered environmental, social, and engineering challenges. The dam currently offers power generation, flood control, and improved navigation, but it has also resulted in ecological and cultural consequences.
15. The Big Dig Project in Boston
The Big Dig Project was a transportation infrastructure project in Boston, Massachusetts, intended to replace an old elevated highway with a newer tunnel system. Completed in 2007, it serves as one of the most complex and costly construction endeavours in US history. Despite facing many delays, cost overruns and engineering challenges, the project successfully improved traffic flow and urban aesthetics but also resulted in accidents, lawsuits, and financial burdens.
16. The Uber Disruptive Business Model Project
The Uber Disruptive Business Model Project was a startup that introduced a new ride business model that disrupted the taxi-cab industry by connecting riders with drivers via a mobile app. Launched in 2010, this project required innovative technology, marketing and regulatory strategies and faced legal actions and ethical challenges related to labour, safety, and competition. Uber has since then dominated the market with its ride-sharing business plan.
17. The Netflix Original Content Development Project
The Netflix Original Content Development Project was an initiative created to launch its original content for its platform. This launch by the online streaming giant in 2012 was a huge success for the company. The project required huge investments in content creation, distribution and marketing and resulted in award-winning shows and films that redefined the entire entertainment industry’s business model.
18. The Tesla Electric Car Project
The Tesla Electric Car Project was a revolutionary project that aimed to compete for its electric vehicles with gasoline-powered vehicles. The project required a strong project management plan that incorporated innovation, sustainability, and stakeholder engagement, resulting in the successful launch of the Tesla Roadster in 2008 and subsequent models. Tesla has one-handedly revolutionised the entire automobile industry on its own.
19. The Johnson & Johnson Tylenol Crisis Management Project:
The Johnson & Johnson Tylenol Crisis Management Project was a case study in crisis management in 1982. The project required quick and effective decision-making skills, stakeholder communication, and ethical leadership in response to the tampering of Tylenol capsules that led to deaths.
20. The Airbnb Online Marketplace Platform Project
The Airbnb Online Marketplace Platform Project was a startup that created an online platform which connected travellers with hosts offering short-term rental accommodations in flights. The project required innovative technology, user experience design and stakeholder management. Airbnb’s success has led to the disruption of the hospitality industry and inspired many other project case study examples of sharing economy platforms.
Future developments in project management include all the insights on the increased use of artificial intelligence, agile methodologies, hybrid project management approaches, and emphasis on sustainability and social responsibility, along with many more developing ideas that will address the evolving market innovations.
The project management case study examples illustrate real-life examples and the importance of project management in achieving project success. The cases show the use of innovative technologies, tools, techniques, stakeholder engagement, crisis management, and agile methodologies.
Project Management also highlights the role of ethical leadership and social responsibility in project management. To learn more and more about case studies, upGrad, India’s leading education platform, has offered an Advanced General Management Program from IMT Ghaziabad that will equip you with in-demand management skills to keep up with the changing trends!
Something went wrong
Project Management is extensive planning, executing, monitoring and closing of a project before its deadline. Project management ensures accuracy and efficiency across all organs of a project, right from its inception to its completion.
Project Management case studies are real-life examples of projects to put an insight into all the tools, techniques and methodologies it provides.
The role of a project manager is to ensure that all day-to-day responsibilities are being met by the resources deployed in a certain project. They have the authority to manage as well as lead the functioning members as well.
Certification
16 Hrs Live Expert-Led Sessions
14 Case Studies, 3 Mock Tests
View Program
Master's Degree
Dual Credentials
Job Assistance
16+ Hrs Expert-Led Sessions
5 Simulation Exams, 8 Mock Tests
24 Hrs Live Expert-Led Training
Earn 24 PDUs and 24 SEUs
36 Hrs Live Expert-Led Training
Premium 2000+ Question Bank
32 Hrs Live Expert-Led Training
Earn 32 PDUs and SEUs
Complimentary On-Demand Course
1 Year SAFe® Community Membership
88 Hours On-Demand Learning
Training by top CSTs
16 Hrs Live Expert-Led Training
Earn 16 PDUs and 16 SEUs
AACSB accredited
Training by Top-Notch SPCs
3 Day Leadership Summit in Dubai
Ivy League School
Executive PG Program
Offline Campus Experience
PG Certification
6-10.5 Months
2500+ Students Enrolled
EQUIS & AMBA Accredited
Executive Coaching
Simulations, 5 Mock Tests
Instructor Led Model
16-Hrs Live Expert-Led Sessions
Earn 16 SEUs and 16 PDUs
16+ Hrs Expert-Led Training
AMBA, AACSB & NIRF Accreditation
24+ Hrs Expert-Led Sessions
Simulation Exams, 24 PDUs
35 Hrs Live Expert-Led Training
35 PD Hrs, 35 CDUs & 35 PDUs
24-Hrs Live Expert-Led Sessions
Activities and Case Studies
8+ Hrs Expert-Led Sessions
Interactive Sessions, Activities
36+ Expert-Led Training
5 Simulation Exams, Projects
21 Hrs Live Expert-Led Training
Earn 21 CDUs and 21 PDUs
2-Day Live Expert-led Training
Simulations, 4 Mock Tests
16 Hours of Instructor-Led Sessions
Simulation Exams and Mock Tests
Earn 16 PDUs and 16 SEUs
24-Hrs Live Expert-Led Training
Earn 24 SEUs and 24 PDUs
Learn more about the education system, top universities, entrance tests, course information, and employment opportunities in Canada through this course.
Advance your career in the field of marketing with Industry relevant free courses
Build your foundation in one of the hottest industry of the 21st century
Master industry-relevant skills that are required to become a leader and drive organizational success
Build essential technical skills to move forward in your career in these evolving times
Get insights from industry leaders and career counselors and learn how to stay ahead in your career
Kickstart your career in law by building a solid foundation with these relevant free courses.
Stay ahead of the curve and upskill yourself on Generative AI and ChatGPT
Build your confidence by learning essential soft skills to help you become an Industry ready professional.
Learn more about the education system, top universities, entrance tests, course information, and employment opportunities in USA through this course.
by Kamal Jacob
19 May 2024
by Nitin Gurmukhani
05 Mar 2024
by Keerthi Shivakumar
23 Jan 2024
24 Sep 2023
15 Sep 2023
14 Sep 2023
04 Sep 2023
24 Aug 2023
An official website of the United States government
Here’s how you know
Official websites use .gov A .gov website belongs to an official government organization in the United States.
Secure .gov websites use HTTPS A lock ( Lock A locked padlock ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.
Free Cyber Services #protect2024 Secure Our World Shields Up Report A Cyber Issue
By Jen Easterly, Director, Cybersecurity and Infrastructure Security Agency
On April 30 th , the White House released National Security Memorandum-22 (NSM) on Critical Infrastructure Security and Resilience , which updates national policy on how the U.S. government protects and secures critical infrastructure from cyber and all-hazard threats. NSM-22 recognizes the changed risk landscape over the past decade and leverages the enhanced authorities of federal departments and agencies to implement a new risk management cycle that prioritizes collaborating with partners to identify and mitigate sector, cross-sector, and nationally significant risk. The culmination of this cycle is the creation of the 2025 National Infrastructure Risk Management Plan (National Plan)—updating and replacing the 2013 National Infrastructure Protection Plan —and will guide federal efforts to secure and protect critical infrastructure over the coming years.
As the National Coordinator for critical infrastructure security and resilience, the Cybersecurity and Infrastructure Security Agency (CISA) will develop this National Plan to be forward-looking and employ all available federal tools, resources, and authorities to manage and reduce national-level risks, including those cascading across critical infrastructure sectors. CISA will look to its partners to help us and the other Sector Risk Management Agencies (SRMAs) over the course of the year as we develop this foundational document.
The National Plan Must Account for the Evolution of Threats, Vulnerabilities, and Consequences
Building off the priorities of NSM-22, the 2025 National Plan will articulate how the U.S. government will collaborate with partners to identify and manage national risk. This will be an evolution from the 2013 National Plan which described risk management as “the cornerstone” to strengthening critical infrastructure security and resilience. Eleven years later, the spirit of this concept holds true; yet it must evolve due to pervasive vulnerabilities and an elevated threat landscape, which could lead to cascading regional and national consequences. Fortunately, over that same decade, Congress and successive administrations have established new agencies, authorities, and collaborative partnerships that empower a whole-of-society approach to national risk management. As the National Coordinator, CISA will be the primary driver for operationalizing this approach through the National Plan.
The National Plan will be Informed by a New Risk Management Cycle
NSM-22 details a new risk management cycle that requires SRMAs to identify, assess, and prioritize risk within their respective sectors and develop sector risk management plans to address those risks. With these risk assessments and risk management plans, CISA will identify and prioritize systemic, cross-sector, and nationally significant risk through a cross-sector risk assessment. This assessment will enable CISA to prioritize systemic risk reduction efforts—detailed in the National Plan—that the U.S. government will take in collaboration with relevant federal, state and local, private, and international partners. Most importantly, the National Plan will recognize that the U.S. government cannot make all critical infrastructure immune from all threats and hazards. Rather, it will detail U.S. government efforts to make critical infrastructure resilient against prioritized risks based on the 16 sector’s risk assessments and CISA’s cross-sector risk assessments. All the while, CISA and other federal partners will work closely with SRMAs to manage their unique sector risks.
We Need You for Us to be Successful
This will be a fundamentally new approach to U.S. government risk management. In this era of technological advancements and dynamic global volatility, the security and resilience of our critical infrastructure are of paramount importance. Essential systems, including energy grids, water systems, transportation networks, healthcare facilities, and communication systems, are vital for public safety, economic stability, and national security. The increasing interconnectivity of critical infrastructure systems, reliance upon global technologies and supply chains, and geopolitical tensions make these systems susceptible to a myriad of threats. Addressing these risks will require a coordinated national effort by federal agencies; State, Local, Tribal, and Territorial (SLTT) governments, infrastructure owners and operators, and other stakeholders across the critical infrastructure community.
As those responsible for the security and resilience of U.S. critical infrastructure, we must collectively address emergent risks and an uncertain future while remaining vigilant against longstanding threats like terrorism, natural disasters, and targeted violence. Indeed, trusted, sustained, and effective partnerships between the federal government and private-sector and SLTT partners is the foundation of our collective effort to protect the nation’s critical infrastructure.
Put simply, the 2025 National Plan will not succeed unless our partners collaborate with us to inform its development and its eventual implementation. We ask that you work with your respective SRMAs through the development of your sector risk assessments and sector risk management plans, as these will be core inputs into the National Plan. You can also contact us at [email protected] for any of your ideas. These inputs will be invaluable as we develop a plan that allows the U.S. government to better prioritize our risk mitigation efforts and reduce risk for the critical infrastructure that underpin American society.
For more information on the NSM-22 and CISA’s role as National Coordinator, visit CISA National Security Memorandum on Critical Infrastructure Security and Resilience | CISA .
Ncswic releases the ncswic video series, prepared together – cyber storm ix recap, securing tomorrow: a recap of cisa’s cyber resilient 911 symposium (central region), opening statement by cisa director jen easterly at the update on foreign threats to the 2024 elections hearing.
IMAGES
VIDEO
COMMENTS
The purpose of this qualitative single case study was to explore the communication strategies some project managers use to engage stakeholders and improve project performance. The target population consisted of five project managers selected from a Nigerian oil and gas company who had used effective communication strategies to
The more complex your project, the more effectively you can manage your communications with stakeholders through the use of a portal solution. You might utilize the portal to share all communications about the project and eliminate the need for excessive face-to-face, virtual or audio conference meetings.
More effective communication = Better project management is obviously known to everyone in project management, but we do face difficulties in implementing it due to various factors like the nature of the project, structure of the organization etc. About 90% of the time in a project is spent on communication by the project manager.
Communication: The Message Is Clear December 2013 4 2013 Project Management Institute, Inc. CASESTUDY COMMUNICATION IN ACTION Organization: NorthWestern Energy, Sioux Falls, South Dakota, USA Industry: Utilities Lesson Learned: Communicating with citizen stakeholders increases public support despite costly and disruptive engagements. NorthWestern Energy was confident its US$350 million ...
Even without managers' regular engagement in problem-solving, communication about its importance can promote more problem-solving among frontline workers. By explaining some of the variation in responsiveness to operational failures, this study empowers managers to adjust their approach to stimulate more problem-solving among frontline workers.
The informed communication strategy allows managers to structure the information flow in a better and more controlled manner and to avoid the costs caused by lack of effective and timely communication. ... Färber K. The impact of cultural differences on project stakeholder engagement: a review of case study research in international project ...
performances in project teams. The purpose of this multiple case study was to explore the strategies used by project managers in the health care industry to strengthen communication within project teams. The conceptual framework for the study was McQuail's mass communication theory and Craig's communication theory. Participants
Abstract. The communication project is a key factor to achieve good results in the development of a project; this includes the processes of planning, collecting, creating, storing, controlling and distributing information in a timely manner. In this context, the general objective of the research was to evaluate the communications management for ...
The Big Project. Collaborative Process and Communication Plan. A Simple Metric Goes a Long Way. Art Cabanban A Little Piece of a Big Pie. Starting Off With a Simple Project Dashboard. Executive Project Metrics. Dragan Z. Milosevic, Peerasit Patanakul, and Sabin Srivannaboon Our Cable Business. Executive Dashboard
Managing stakeholder communication is a fundamental part of any construction project. Like any aspect of consequence, it needs to be conducted in an effective way to ensure success in the project ...
A Case Study of Domino's Pizza's Crisis Communication Strategies. Abstract. Domino's Pizza was embroiled in a viral crisis situation when two rogue employees posted videos of adulterated food on YouTube in April 2009. Tim McIntyre, Vice President of Communications, was part of the internal team that delivered the company's crisis ...
Project management is a crucial discipline that involves the application of knowledge, skills, tools, and techniques to project activities. Its primary goal is to meet specific project requirements by carefully planning, executing, controlling, and closing projects within defined constraints. These constraints typically include factors such as ...
O'Rourke, J. S. (2013). Management communication: A case-analysis approach. Boston: Prentice Hall. ... Newton Square, PA: PMI. Google Scholar; Ramsing, L. (2009). Project communication in a strategic internal perspective. Corporate Communications, 14(3), 345-357. ... This paper is a response to the call in the Rethinking Project Management ...
Case Studies in Strategic Communication (CSSC) is dedicated to the study of strategic communication through the case study form. Case studies illustrate the strategies, tactics, and execution of communication campaigns through in-depth coverage of a single situation. CSSC is a peer-reviewed online publication housed at the University of ...
Research on crisis communication has mainly focused on defensive strategies to restore organizational reputation (Coombs, 2007) and on the ways in which organizations explain themselves to stakeholders, such as the public and the media, with the aim of countering negative perceptions.Situations where a criminal organization intentionally creates a situation that aims to destroy the public ...
Project management is not just putting together a project plan using work breakdown structures, calculating critical paths, and developing charts and timelines. Even the best project plan will not be successful without project communication. Effective, regular project communication requires planning and tailoring to the appropriate recipient of the information. Effective project communication ...
CASE STUDY: Louisiana State University. Kathleen Searles, Ph.D. ... Plan . Project Evaluation • Performance analysis • ADVANCE Toolkit • Communication Studies • Meta Evaluation (formative and summative processes) Performance Analysis. LSU ADVANCE Catalyst Organizational Change Model.
In fact, a recent estimate claims that the cost in the U.S. alone are close to $4 billion annually! [1] Poorly-worded or inefficient emails, careless reading or listening to instructions, documents that go unread due to poor design, hastily presenting inaccurate information, sloppy proofreading — all of these examples result in inevitable costs.
Objectives: This study investigates the preference of email communication relative to other communication mediums in project environments, and the effect of email communication on feelings of ...
Real-world or live projects offer an alternative to learning strategic design skills and approaches such as design research, experience prototyping, visioning, co-design or systems thinking. In this paper, we report a case study of a graduate studio live project exploring the use of strategic design skills.
Through global case studies and protagonist examples, you will explore topics that set you on a path to strengthen your public leadership skills, including leadership and team development, resource and budget planning, talent recruitment and retention, strategic communications and crisis management, and risk planning and mitigation tactics.
Rather than discussing case study in general, a targeted step-by-step plan with real-time research examples to conduct a case study is given. Introduction In recent years, a great increase in the number of students working on their final dissertation across business and management disciplines has been noticed ( Lee & Saunders, 2017 ).
Trolling and sick burns John Fetterman's winning social media strategy against Mehmet Oz in the 2022 Pennsylvania Senate campaign. Sarah VanSlette. 1-15. vanslette_trolling. Everything Barbie all at Once "A Marketing Campaign for the Ages". Regina Luttrell, Ph.D, Carrie Welch.
The Opera House stands as a symbol of perseverance and successful project management in the face of humankind. 2. The Airbus A380 Project. The Airbus A380 Project is a project management case study showcasing the challenges encountered during developing and producing the world's largest commercial aircraft.
This ambiguity leads to errors, missed steps in the process, conflicts, and other issues. All these scenarios will result in delays or budget overruns in the end. In this case, multiple stakeholder communications and changes in client requirements caused the project to fail. As a result, internal conflicts will arise, with teams blaming each ...
The project management lifecycle is a step-by-step framework of best practices used to shepherd a project from its beginning to its end. This project management process generally includes four phases: initiating, planning, executing, and closing. Some may also include a fifth "monitoring and controlling" phase between the executing and ...
On April 30 th, the White House released National Security Memorandum-22 (NSM) on Critical Infrastructure Security and Resilience, which updates national policy on how the U.S. government protects and secures critical infrastructure from cyber and all-hazard threats. NSM-22 recognizes the changed risk landscape over the past decade and ...